Technical & Financial PFS - Supplementary Information
Released
Released
Announcement PDF
criticalmineralsgroup.com.au
(+61) 755 555 077
Level 15, 100 Edward Street, Brisbane QLD 4000, Australia
info@criticalmineralsgroup.com.au
TECHNICAL AND FINANCIAL PRE-FEASIBILITY STUDY -
SUPPLEMENTARY INFORMATION
Critical Minerals Group Limited (ASX: CMG) ("CMG" or the "Company") is pleased to
provide supplementary information to the Technical and Financial Pre-Feasibility Study
(“PFS”) released on 20 July 2026 (“PFS Announcement”). The Project comprises the
development of an integrated open-cut vanadium mine near Julia Creek in north-
western Queensland and a Vanadium Electrolyte (“VE”) manufacturing facility at the
Parkes Special Activation Precinct in central New South Wales.
Capital Expenditure
The Project’s CAPEX covers initial, sustaining and replacement, and life-of-mine (LOM)
capital, representing all costs to develop, operate, and maintain the project and is set
out in Table 1.
• Initial capital includes expenses to fully launch operations, including the
development of the Lindfield mine and processing facilities, vanadium electrolyte
facility construction, non-process and utility infrastructure, indirect costs, and
contingency.
• Sustaining and replacement capital funds the ongoing operation integrity, such as
equipment replacements, process upgrades, and mine-related items.
Capital Allocation by Major Area
Capital spending is distributed as follows:
• Mine and Processing plant: Plant development including processing circuits and
waste and residue management.
• Electrolyte Facility: Manufacturing plant setup, expansion capability.
ASX Announcement
ASX: CMG
21 July 2026
2
• Infrastructure: Utilities, roads, dams, storage, accommodation, communications,
administration and workshop facilities.
• Indirects & Contingency: Engineering, temporary works, commissioning, owner’s
costs, risk-based contingency.
The initial capital expenditure to develop the mine, processing facilities and vanadium
electrolyte facilities is AUD$981 million, which includes a contingency of 10%. The
sustaining capital to maintain the facilities over the operational period of 31 years is
estimated at AUD$306 million. The total life-of-mine capital is estimated to be
AUD$1,287 million.
Table 1 Capital Costs
Capital Initial
($m)
Sustaining
($m)
Total
($m)
Processing Plant — beneficiation,
hydrometallurgy, product recovery
576 200 776
Non-Process Infrastructure (mine,
roads, dams, storage, bore, utilities,
fencing, workshop, ancillary facilities)
49 15 64
On-site Sulphuric Acid Plant 192 45 237
Vanadium Electrolyte Facility — 72
ML/pa (3 Mtpa)
164 46 210
Total (incl 10% contingency) 981 306 1,287
The capital costs include direct and indirect costs and owner’s costs. Sustaining
capital costs have been based on between 1-1.5% of equipment costs.
Operating Expenditure
The Lindfield Project’s operating costs vary across the mine and processing schedule
as the grade varies through the mineralised material. This occurs both within the
different units of TLBA, TLBB and TLBD as they are processed and between the units as
each of the different units TLBA, TLBB and TLBD have different grade ranges1
. Figures 7
and 9 of the PFS Announcement identify the mine sequence and processing of each
unit. Each of the operating cost centre variables change, with the largest impact
occurring in the processing-related items1
. Using 2033 as an example year, once the
operation is planned to be in steady-state operations, the operating cost is estimated
at AUD$74.96 per feed tonne of economically mineable mineralised material, or
USD$6.16 / lb of V2O5 produced2
. The costs range from USD$5.90 early in the Project’s
operational life to USD$8.70 as the grade decreases in the later part of the operation.
1
Refer to Table 4 (page 9) of the PFS Announcement
2
Refer to Figures 7 (page 14) and 9 (page 16) of the PFS Announcement
3
Table 2 Operating Cost for the production of V2O5.
Cost Centre AUD$/ feed tonne AUD$/ V2O5 t USD/V2O5 lb
Mining 3.35 906 0.28
Contractor Margin 0.37 101 0.03
Processing Fixed 4.68 1,265 0.38
Reagents 58.34 15,773 4.79
Power 3.43 928 0.28
Water 0.19 51 0.02
Logistics 0.36 98 0.03
Overheads Lindfield 0.34 91 0.03
Lindfield Labour 1.72 465 0.14
Sub Total excl Royalty and
Govt Charges
72.78 19,677 5.98
Royalty 2.17 588 0.18
Total Operating Cost 74.96 20,265 6.16
The MRE breakdown for the different horizons TLBA, TLBB and TLBD into Mineral Resource
Categories Inferred and Indicated is per the following table, as advised by CMG in a
market release on 10 May 2024 “Table 2” under the title “Significant Increase to Lindfield
Project Mineral Resource Estimate Following Recent Drilling Campaign”.
Table 3 MRE breakdown of mineralised material
In Situ Mineral Resource (Mt at V2O5 wt%)
Horizon Indicated Inferred Total
TLBA 259 at 0.22% 120 at 0.23% 378 at 0.22%
TLBB 152 at 0.48 63 at 0.45% 214 at 0.47%
TLBC - - -
TLBD 80 at 0.33% 40 at 0.35% 120 at 0.34%
TLBE - - -
Total 491 at 0.32% 222 at 0.31% 713 at 0.32%
4
COMPETENT PERSON STATEMENTS
Economically Mineable Mineralised Material (EMMM)
The information in this announcement that relates to Mine Planning, Scheduling,
Assessment of EMMM at the Project is based on information compiled by Pat Kelly, a
Competent Person who is a Member of the Australasian Institute of Mining and
Metallurgy (AusIMM). Pat Kelly is a Mining Engineer and Chief Operating Officer of
Critical Minerals Group. Pat Kelly has sufficient experience that is relevant to the style of
mineralisation and type of deposit under consideration, and to the activity being
undertaken to qualify as a Competent Person as defined in the 2012 Edition of the
‘Australasian Code for Reporting of Exploration Results Mineral Resources and Ore
Reserves’. Pat Kelly consents to the inclusion of the matters based on his information in
the form and context in which it appears.
Mineral Resource Estimate
The information in this announcement that relates to Mineral Resource Estimates at
the project is based on information compiled by Adrian Buck, a Competent Person who
is a Member of the Australasian Institute of Mining and Metallurgy (AusIMM). Adrian
Buck is the Principal Geologist – Australia, and is employed by, Measured Group. Adrian
Buck has sufficient experience that is relevant to the style of mineralisation and type of
deposit under consideration, and to the activity being undertaken to qualify as a
Competent Person as defined in the 2012 Edition of the ‘Australasian Code for
Reporting of Exploration Results Mineral Resources and Ore Reserves’. Adrian Buck
consents to the inclusion of the matters based on his information in the form and
context in which it appears. The Mineral Resource Estimates were previously reported
the Project in CMG’s ASX announcement entitled “Significant Increase to Lindfield
Project Mineral Resource Estimate Following Recent Drilling Campaign” released to ASX
on 10 May 2024 which is available to view at www.asx.com.au. The Company confirms
that it is not aware of any new information or data that materially affects the
information included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in the market
announcement continue to apply and have not materially changed. The Company
confirms that the form and context in which the competent persons findings are
presented have not been materially modified from the original market announcement.
FORWARD-LOOKING STATEMENTS
This announcement contains certain statements which may constitute “forward
looking statements.” Such statements are only expectations or beliefs and are subject
to inherent risks and uncertainties which could cause actual values, results or
performance achievements to differ materially from those expressed or implied in this
presentation. No representation or warranty, express or implied is made by CMG that
5
any forward-looking statement contained in this presentation will occur, be achieved
or prove to be correct. Readers are cautioned against relying upon any forward-
looking statement.
This announcement has been authorised for release by the Board of Directors of
Critical Minerals Group Limited.
For further information, please contact:
Scott Winter
Chief Executive Officer
Critical Minerals Group Limited
Email: info@criticalmineralsgroup.com.au
Phone: +61 7 3132 3504
About Critical Minerals Group Limited
Critical Minerals Group Limited (ASX: CMG) is a Queensland-based vertically
integrated vanadium developer. CMG is advancing the Lindfield Vanadium Project in
north-western Queensland – comprising an open-cut mine and a Vanadium
Electrolyte manufacturing facility at the Parkes Special Activation Precinct in NSW,
targeting the rapidly growing long-duration energy storage market served by
Vanadium Flow Batteries.