Quarterly Activities Report & Appendix 5B for the
period ending 31 December 2023
Key Highlights
•
•
•
•
•
•
Finalisation of the Lindfield Project Scoping Study
o CMG completes a Scoping Study that identifies the Lindfield Project as having both
the technical and financial attributes to develop a vanadium mine capable of
producing approximately 10,500 tonnes of vanadium pentoxide with the potential
to produce High Purity Alumina as a secondary product.
Board approval for next phase of feasibility study work
o Lindfield Vanadium Project study work to continue with the pilot plant supporting
the larger scale testing, and Lava Blue license enabling further investigation into
HPA production.
Secured Lava Blue license for the production of High Purity Alumina and associated byproduct minerals
o CMG executes a License Agreement with Lava Blue Ltd to enable the detailed
investigation and development of the HPA and other potential value-adding coproducts from the Lindfield Project.
Potential Joint Venture with True North Copper for the development of copper assets
o Non-binding term sheet for farm-in executed with TNC in December 2023, under
which TNC may acquire a 75% interest in EPM 27998 and 27999.
Commencement of environmental background studies and engagement with Coordinator
General Office
Pilot Plant test work planning underway
Critical Minerals Group Limited (ASX:CMG), (Critical Minerals Group, CMG, or the Company) is
pleased to provide shareholders with the following update in relation to the Company’s activities for
the quarter ended 31 December 2023 (Quarter).
Critical Minerals Group Limited | ACN 652 994 726 | Level 4, Gold Tower, 10 Eagle Street, Brisbane QLD 4000
info@criticalmineralsgroup.com.au | (07) 5555 5077 | www.criticalmineralsgroup.com.au
Critical Minerals
Company Projects
Image 1: Map of CMG’s projects.
Source: Queensland Government, GeoResGlobe, Available at: https://georesglobe.information.qld.gov.au/
Lindfield Project (EPM 27872)
The “Lindfield Project” comprises Queensland exploration permit for mining (EPM) 27872 and
consists of 92 sub-blocks, covering 295km². The Lindfield Project is located approximately 30km northeast of the township of Julia Creek. The project area lies close to main infrastructure facilities and is
intersected by the Flinders Highway and the Great Northern Railway Line at the southern end of the
tenement.
The Lindfield Project is considered highly prospective for vanadium and High Purity Alumina (HPA).
The Lindfield Project area is characterised by the presence of the Toolebuc Formation, Allaru
Mudstone, and quaternary sediments.
Drilling for Pilot Scale Test work
A targeted drill program involving 14 x 4C and 2 x 8C core holes was successfully completed in late
September 2023 to gather mineralised material samples for a Pilot Scale testing program in a
Vanadium Processing Pilot Plant (VPPP) and to improve confidence in the existing Mineral Resource
Estimate at the flagship Lindfield Project. Assaying is underway and it is expected that an updated
Mineral Resource Estimate will be issued towards the end of the March quarter.
Metallurgical test work
Test results received during the quarter included carbon analysis of flotation products to enable
estimation of carbon emissions during roasting, deeper investigations into roasting/leach chemistry
profiles to improve Solvent Extraction (SX) performance, analysis of flotation tailings for further
optimisation of flotation outcomes, settling tests on flotation products and silica coagulation tests to
reduce silica reporting through to Ammonium Metavanadate (AMV).
Environmental studies
The Company has engaged environmental consultants to carry out background ecological studies
across the Lindfield tenement in order to secure baseline data for the region. The initial review
program was carried out successfully before the wet season commenced. Water monitoring
continued throughout the period to assist with the data required to generate an appropriate ground
water model across the project area. CMG has engaged with the Coordinator-General’s office to
present the Lindfield project and to understand the appropriate regulatory pathways through the
environment and development approvals.
Scoping Study Completion
The Company announced on the 9th of November 20231 that it had successfully completed the
Lindfield Vanadium Project Scoping Study and released the major findings from that study. The key
findings from that study supported the commencement of the next phase of detailed feasibility study
on the Lindfield Project along with the larger scale pilot plant testwork. The key findings include:
•
The results from the scoping study support the conclusion that the Lindfield Project has both
the technical and financial attributes to develop a successful 4 million tonne per annum ROM
vanadium mine producing approximately 10,500 tonnes of vanadium pentoxide.
•
The resources supported a long mine life and the test-work indicated favourable metallurgical
recovery results for the upper seam which have warranted further investigation and analysis.
•
The financial analysis indicated a viable IRR (post tax) and a compelling positive NPV using the
favourable metallurgical test results and the estimate of operational and capital costs.
•
The test work carried out using the Lava Blue technology produced a 4N HPA product. The
additional HPA has also been confirmed as a potential product which could provide future
upside for the project. Similarly Molybdenum was found to build up to economically viable
levels which support Molybdenum as an additional by-product.
•
High level investigation into site and regional infrastructure and utilities including power,
water and gas indicate that these are available to support the development of the vanadium
mine in the Julia Creek region. There is further work required to optimise these for cost and
efficiency.
1
2924-02737695-2A1486698 (markitdigital.com)
Figtree Creek Project (EPM 27998) and Lorena Surrounds Project (EPM 27999)
The “Figtree Creek Project” consists of 22 sub-blocks covering 70km². The Figtree Creek Project is
located approximately 10 km southeast of the township of Cloncurry and is 5km from the main
infrastructure corridor of the Flinders Highway and the Great Northern Railway line.
The Figtree Creek Project is considered prospective for iron oxide copper and gold mineralization
based on historical surface sampling, local structural geology with similar rock types and structures
present in the Figtree Creek Project area to that of the Great Australian Mine style of copper-gold
mineralisation (located 3km north of the project) and electromagnetic anomalies identified.
The project area has several rock chip samples, soil samples and stream sediment samples showing
anomalous copper and gold assays.
The “Lorena Surrounds Project” consists of 16 sub-blocks covering 51km². The Lorena Surrounds
Project is located 15km east of Cloncurry and intersects main infrastructure of the Flinders Highway
and Great Northern Rail Line at the southern end of the tenement.
The Lorena Surrounds Project is considered prospective for iron oxide copper and gold mineralization
based on historical drilling, local structural geology and electromagnetic anomalies identified.
The Company executed a non-binding term sheet with TNC in December 2023 under which TNC may
farm-in to EPM 27998 (forming the Figtree Creek Project) and EPM 27999 (forming the Lorena
Sounds Project), which are both located in Mount Isa, Queensland (Tenements) for the
development of copper assets (see the Company’s ASX announcement dated 7 December 2023).
TNC may acquire a 75% interest in the Tenements if it incurs at least $750,000 of expenditure in
carrying out various farm-in activities over a three-year period. If TNC meets its expenditure
obligations and elects to exercise the option, a joint venture will be formed, with TNC to manage the
joint venture.
Formal (binding) documents are currently being finalised and a further announcement will be made
once those documents have been executed.
Whinmoor Project (EPM 28631)
The “Whinmoor Project” consists of 100 sub-blocks covering 320 km². The Whinmoor Project is
located 60km north of Julia Creek.
The Whinmoor Project intends to extend on exploration by previous explorers and known extensions
to vanadium mineralisation in the Company’s Lindfield Project.
A review of the known historical information with respect to exploration activities on and around
EPM28631 was conducted in the December quarter resulting in the identification of one primary and
two secondary drill targets. Development and implementation of an actual drilling program will be
subject to Board approval and available funding.
Lara Downs Project (EPM 28635 Application)
The Company has applied for EPM 28635 in relation to the “Lara Downs Project”. As at the end of
the Quarter, this application was still in progress and had not yet been granted. EPM28635 was
advertised under Section 29 (notices for Native Title) on 6th December 2023 and is subject to a 4
month notification period.
The Lara Downs Project consists of 118 sub-blocks covering 378 km². The Lara Downs Project is located
60km northwest of Julia Creek.
The Lara Downs Project intends to extend on exploration by previous explorers and known extensions
to Vanadium mineralisation in the Company’s Lindfield Project.
As the Lara Downs Project tenement is only at the application stage, the Company has not yet
performed significant and detailed geological analysis, interpretation and exploration targeting.
No substantive exploration activities were undertaken during the Quarter, and no field work has been
undertaken as the Lara Downs Project is still in the application phase.
Lindfield North Project (EPM 28636 Application)
The Company has applied for EPM 28636 in relation to the “Lindfield North Project”. As at the end
of the Quarter, this application was still in progress and had not yet been granted. EPM28636 was
advertised under Section 29 (notices for Native Title) on the 6th of December 2023 and is subject to a
4-month notification period.
The Lindfield North Project consists of 36 sub-blocks covering 115 km². The Lindfield North Project is
located 65km north of Julia Creek.
The Lindfield North Project intends to extend on exploration by previous explorers and known
extensions to Vanadium mineralisation in the Company’s Lindfield Project.
As the Lindfield North Project tenement is only at the application stage, the Company has not yet
performed significant and detailed geological analysis, interpretation and exploration targeting.
No substantive exploration activities were undertaken during the Quarter, and no field work has been
undertaken as the Lindfield North Project is still in the application phase.
Upcoming Work Programme
The Company is planning the following exploration and work activities during the quarter ending 31
March 2024.
Lindfield Project
During the March quarter, the Company plans to carry out the following work:
•
•
•
•
•
•
Commence a Prefeasibility study with a preferred provider.
Metallurgical test works including:
o Additional flotation aiming at decreasing vanadium losses;
o Review outcomes of settling tests on front-end products and commence testwork on
back-end products;
o Continue investigations into optimal flowsheet configuration for molybdenum
recovery;
o Locked cycle testing in flotation and SX/AMV to model the streams to optimise ahead
of the pilot plant testing; and
o A new round of HPA test work with Lava Blue aimed at options to further improve
product quality and to generate product for downstream investigations.
Complete assaying of the recently completed drill program in readiness for pilot plant testing
and Mineral Resource Estimate update.
Planning and preparation for a pilot plant metallurgical test program that will incorporate
each aspect of the process flow sheet. Include determination of the composition of samples
for pilot testing and variability testing.
Finalise and implement timeline and plan for works/studies required for the various
government approvals required prior to commencement of construction and operation
Commence Electrolyte manufacturing scoping study.
Figtree Creek Project and Lorena Surrounds Project
As these tenements are now subject to a term sheet for a farm-in agreement with TNC, the Company
will work towards progressing the execution of formal documents (and monitor progress and report
any material outcomes as required).
Whinmoor Project
The Company will continue to evaluate the outcomes of the December quarter review to determine
the timing and scope of future works – this will be added to the timeline once internal approvals are
complete.
Lara Downs Project
During the March quarter, the Company plans to continue to progress the tenement application.
Lindfield North Project
During the March quarter, the Company plans to continue to progress the tenement application.
ASX Announcements during the Quarter
This quarterly report contains information released to ASX which has been reported in accordance
with the JORC Code (where required). These announcements can be found on the Company’s website
at https://www.criticalmineralsgroup.com.au/asx-announcements and are listed below for
reference:
6 October 2023
Notice of Annual General Meeting/Proxy Form
27 October 2023
Addendum to 2023 Annual General Meeting
31 October 2023
Quarterly Activities/Appendix 5B Cash Flow Report
31 October 2023
Technology License with Lava Blue
1 November 2023
Results of Scoping Study for Lindfield Vanadium Project
1 November 2023
Pause in Trading
1 November 2023
Trading Halt
3 November 2023
Suspension from Official Quotation
8 November 2023
AGM -Chair Address
8 November 2023
Results of Meeting
9 November 2023
Revised Release of Scoping Study Results
9 November 2023
Reinstatement to Quotation
14 November 2023
Notification – Investor Webinar
15 November 2023
Investor Presentation
7 December 2023
Farm in Agreement
Financial Commentary
The Quarterly Cashflow Report (Appendix 5B) for the Quarter provides an overview of the Company’s
financial activities.
Exploration expenditure for the current period was $474,627. Corporate and other expenditures
amounted to $545,621.
In line with its obligations under ASX listings rule 5.3.5, the total amount paid to directors and their
associates in the period (item 6.1 of the Appendix 5B) was $173,000 and includes the Managing
Director’s salary.
Quarterly Expenditure Review Compared with Prospectus Use of Funds
Exploration expenditure for the Quarter was $474,627. These activities are in line with the use of
funds disclosed in the Prospectus.
As per the Prospectus
Use of Funds
Lindfield Project (EPM 27872)
Earthworks (Drill sites and access)
Maiden Drilling
(for the 2-year period
post Listing)
Actual expenditure for
the Quarter
Actual expenditure to
date
60,000.00
525,000.00
0.00
16,732.00
477,063.47
Geological Model & JORC Resource
update
85,000.00
53,585.05
128,436.91
Metallurgy Test Work
Lab Pilot Plant Test Work
Infill Drilling
Hydrogeological Survey
Geo-tech Works
Baseline Environmental Works
Scoping Study
300,000.00
590,000.00
265,000.00
160,000.00
145,000.00
135,000.00
250,000.00
98,893.75
4,607.50
124,088.15
221,096.00
0.00
151,743.34
41,709.57
0.00
16,681.50
424,290.65
474,627.36
0.00
1,477,753.44
0.00
6,648.00
33,019.73
39,667.73
Native Title
Project Total
Figtree Creek Project (EPM 27998)
Native Title
Desktop Studies
Project Total
2,515,000.00
15,000.00
40,000.00
55,000.00
151,743.34
41,709.57
Lorena Surrounds Project (EPM
27999)
Native Title
Desktop Studies
Project Total
Whinmoor Project (EPM 28631)
Native Title
Desktop Studies
Project Total
SUB-TOTAL
Expenses of the offer outstanding at
date of Prospectus *
Working Capital
Total
15,000.00
45,000.00
60,000.00
0.00
0.00
17,672.54
0.00
17,672.54
0.00
0.00
0.00
2,630,000.00
0.00
474,627.36
3,723.95
17,189.00
20,912.95
1,556,006.66
643,022.60
0.00
335,328.00
1,909,047.67
5,182,070.27
549,030.57
1,023,657.93
2,319,570.76
4,210,905.42
JORC Statement
The information in this announcement relating to Mineral Resources is extracted from the Company’s
ASX announcement titled ‘Lindfield Vanadium Project Delivers Improved Mineral Resources Estimate
with Grade and Tonnage to World Class Scale’ dated 16 May 2023 which is available to view on
www.asx.com.au. The Company confirms that it is not aware of any new information or data that
materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The Company confirms that the
form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcement.
Production targets and forecast financial information
The information in this announcement that relates to production targets and forecast financial
information derived from a production target is extracted from the Company’s ASX announcement
dated 9 November 2023 titled ‘CMG successfully completes Scoping Study for Flagship Lindfield
Vanadium Project’ available to view at www.asx.com.au (Scoping Study Announcement). The
Company confirms that all material assumptions underpinning the production targets and forecast
financial information derived from production targets set out in the Scoping Study Announcement
continue to apply and have not materially changed.
Scoping Study cautionary statement
The Scoping Study referred to in this announcement is based on the Scoping Study released by the
Company to ASX in the Scoping Study Announcement.
The Company advised that the Scoping Study has been undertaken to consider development of the
Lindfield Project. It is a preliminary technical and economic study of the potential viability of the
Lindfield Project. It is based on low level technical and economic assessments that are not sufficient
to support the estimation of ore reserves. Further evaluation work and appropriate studies are
required before the Company will be in a position to estimate any ore reserves or to provide an
assurance of an economic development case. There is a low level of geological confidence
associated with any Inferred Mineral Resources and there is no certainty that further exploration
work will result in the determination of Measured or Indicated Mineral Resources or that the
Production Schedule or preliminary economic assessment will be realised.
The Scoping Study is based on the material assumptions outlined in the Scoping Study
Announcement. These include assumptions about the availability of funding. While the Company
considers all the material assumptions to be based on reasonable grounds, there is no certainty that
they will prove to be correct or that the range of outcomes indicated by the Scoping Study will be
achieved.
To achieve the range of outcomes indicated in the Scoping Study, additional funding will be
required. The Company has a supportive shareholder base and has successfully raised capital to
progress the Lindfield Project in the past. However, investors should note that there is no certainty
that the Company will be able to raise the amount of funding required to develop the Lindfield
Project when needed. It is also possible that such funding may only be available on terms that may
be dilutive or otherwise affect the value of the Company’s existing shares. It is also possible that the
Company could pursue other ‘value realisation’ strategies such as a sale, partial sale, or joint
venture of the Lindfield Project. If it does, this could materially reduce the Company’s proportionate
ownership of the Lindfield Project.
The Scoping Study results contained in this announcement relate solely to the Lindfield Project and
do not include Exploration Targets or Mineral Resources defined elsewhere. The Company has
concluded it has a reasonable basis for providing the forward-looking statements included in this
announcement.
Given the uncertainties involved, investors should not make any investment decisions based solely
on the results of the Scoping Study.
Forward-Looking Statements
This announcement may include forward-looking statements. Forward-looking statements include,
but are not limited to, statements concerning planned exploration program and other statements
that are not historical facts. When used in this document, the words such as “could”, “plan”,
“estimate”, “expect”, “intend”, “may”, “potential”, “should” and similar expressions are forwardlooking statements. Although the Company believes that its expectations reflected in these forwardlooking statements are reasonable, such statements involve risks and uncertainties and no assurance
can be given that actual results will be consistent with these forward-looking statements.
This announcement was approved by the board.
For more information:
Scott Winter
CEO and Managing Director
info@criticalmineralsgroup.com.au
(07) 5555 5077
Schedule 1 – Tenement Schedule as at 31 December 2023
Project Name
Location
Tenement
Status
Equity at 30
September
2023
Lindfield
Project
Julia Creek
EPM 27872
Granted
100%
100%
-
Figtree Creek
Project
Cloncurry
EPM 27998
Granted
100%
100%
-
Lorena
Surrounds
Project
Cloncurry
EPM 27999
Granted
100%
100%
-
Whinmoor
Project
Julia Creek
EPM 28631
Granted
100%
100%
-
Lara Downs
Project
Julia Creek
Application
100%
100%
-
Lindfield
North Project
Julia Creek
Application
100%
100%
-
EPM 28635
(application)
EPM 28636
(application)
Equity at 31
December
2023
Changes
during
Quarter
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
CRITICAL MINERALS GROUP LIMITED
ABN
Quarter ended (“current quarter”)
91 652 994 726
31 DECEMBER 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date
(12 months)
$A’000
-
-
(10)
(72)
(d) staff costs
(257)
(891)
(e) administration and corporate costs
(160)
(562)
7
53
-
-
(420)
(1,472)
(475)
(1,261)
(a) exploration & evaluation
(b) development
(c) production
1.3
Dividends received
1.4
Interest received
1.5
Interest and other costs of finance paid
1.6
Income taxes paid
1.7
Government grants and tax incentives
1.8
Other (provide details if material)
1.9
Net cash from / (used in) operating
activities
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
(e) investments
(f)
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date
(12 months)
$A’000
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
2.3
Cash flows from loans to other entities
2.4
Dividends received
2.5
Other (provide details if material)
2.6
Net cash from / (used in) investing
activities
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt
securities
3.3
Proceeds from exercise of options
3.4
Transaction costs related to issues of equity
securities or convertible debt securities (i)
3.5
Proceeds from borrowings
3.6
Repayment of borrowings
3.7
Transaction costs related to loans and
borrowings
3.8
Dividends paid
3.9
Other (provide details if material)
3.10
Net cash from / (used in) financing
activities
(i)
(475)
(1,261)
-
-
-
-
-
-
Payments of $61,328 reclassified from administration and corporate costs to transaction costs related to
issue of equity securities during the December 2022 quarter
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
1,866
3,704
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(420)
(1,472)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(475)
(1,261)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
-
-
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(12 months)
$A’000
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
971
971
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
971
1,866
5.2
Call deposits
5.3
Bank overdrafts
5.4
Other (provide details)
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
971
1,866
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
173
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
8.1
Net cash from / (used in) operating activities (item 1.9)
(420)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(475)
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(895)
8.4
Cash and cash equivalents at quarter end (item 4.6)
971
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
-
$A’000
971
1
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Yes
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer:
Yes. The company has implemented measures to source additional funds for its
operations. Mandates are already in place with brokers to facilitate a capital raise in
the first quarter of 2024, and the Company has a high level of confidence that its
capital raising endeavours will be successful.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Yes, on the basis that the outcome of the capital raising referred to above will be
successful and will generate the required cash to enable the Company to meet its
business objectives.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
31 January 2024
Authorised by:
Board of Directors
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing
Share your feedback
Discover