TECHNICAL AND FINANCIAL PRE-FEASIBILITY STUDY
Critical Minerals Group Limited (ASX: CMG) ("CMG" or the "Company") is pleased to
announce the completion of a Pre-Feasibility Study (“PFS”) for the Lindfield Vanadium
Project. The Project comprises the development of an integrated open-cut vanadium
mine near Julia Creek in north-western Queensland and a Vanadium Electrolyte (“VE”)
manufacturing facility at the Parkes Special Activation Precinct (SAP) in central New
South Wales.
PFS HIGHLIGHTS
Pre-Tax IRR 26.6%
Pre-Tax NPV (AUD) $821M
Post-Tax IRR 18%
Post-Tax NPV (AUD) $458M
Total Capital (AUD) $981M
Payback Period 7 years
Annual ROM Feed 3 Mtpa
Mine Life 31 years
Peak Funding Requirement $736M
Beneficiation Recovery 92%
Process Plant Recovery 74.5%
Av. Annual Pentoxide Production (Yr1-16) 10,577 tonnes
Vanadium Pentoxide Production 236,351 tonnes
Av. Annual VE (Yr 1-16) 73 million litres
Vanadium Pentoxide (VE) Production 1.57 billion litres
ASX Announcement
ASX: CMG
20 July 2026
2
The strong ROI for the combined Lindfield Vanadium Pentoxide and Vanadium
Electrolyte production strategy justifies advancing to Definitive Feasibility Study and
advancing project approvals to support an FID decision in calendar year 2027.
PRE-FEASIBILITY STUDY OVERVIEW
Critical Minerals Group has completed a Pre-Feasibility Study (“PFS”) for its Lindfield
Vanadium Project in Queensland's North West Minerals Province, confirming a
technically executable and financially compelling critical minerals development. The
Study evaluates three production scenarios; 1 Mtpa, 3 Mtpa and 4 Mtpa of run of mine
(ROM) Economically Mineable Mineralised Material (EMMM), built around a vertically
integrated model spanning mine production of vanadium pentoxide (V₂O₅) through to
downstream manufacture of vanadium electrolyte for use in vanadium flow batteries.
The project is structured as a staged development, with a vanadium electrolyte facility
commissioned ahead of the Lindfield Mine using third-party V₂O₅ feedstock, bringing
forward first revenue to 2028 and reducing peak funding exposure relative to a
conventional single stage build.
The PFS has been prepared to an accuracy range of ±25% (March 2026 A$). This is
consistent with industry standards for studies of this nature and with the JORC Code
(2012) and ASX Listing Rules Chapter 5 requirements, applying a 9% discount rate, an
AUD/USD exchange rate of 0.67, and the Australian corporate tax regime. The 3 Mtpa
case has been identified as the preferred development pathway, delivering a pre-tax
IRR of 26.6% and pre-tax NPV of A$821 million, comfortably exceeding the applied cost
of capital. The 4 Mtpa case produces a broadly comparable NPV at materially higher
capital intensity, while the 1 Mtpa case remains technically viable and is retained as a
lower-capital contingency option. Sensitivity analysis confirms the project's returns are
most exposed to vanadium electrolyte price, mineralised material grade and
metallurgical recovery, while being notably insensitive to capital cost and discount
rate.
The Project’s Forward Looking Statements and Production Target are underpinned by
the previously reported Mineral Resource Estimate (“MRE”)1
. The MRE underpinning the
Production Target has been prepared by a competent person in accordance with the
requirements of the JORC Code (2012). No Ore Reserves have been reported with the
PFS. The PFS provided robust assessment of mining options, established the open-pit
configuration, developed an effective method of mineral processing, and included a
financial analysis based on reasonable assumptions on the Modifying Factors.
However, on the basis the mine plan currently includes Inferred Resources, an Ore
Reserve Statement was not pursued at this stage. During the DFS, the Company is
planning additional drill core holes with a view to increasing its geological confidence
1
Refer to ASX Announcement dated 10 May 2024 entitled “Significant Increase to Lindfield
Project Mineral Resource Estimate Following Recent Drilling Campaign”.
3
in its resource estimates, with the ultimate goal of being able to release a Measured
Resource Estimate and maiden Ore Reserves for the Lindfield Project on completion of
the DFS.
The Board to advance the Project from Pre-Feasibility to Definitive Feasibility Study,
with three priority workstreams identified to underpin that transition:
1. completion of the metallurgical pilot plant programme to confirm and improve
vanadium recovery, the single highest impact lever on project value;
2. securing long-term, competitively priced supply agreements for sulphuric acid and
sodium hydroxide, which together represent a significant proportion of processing
operating costs; and
3. advancing government concessional finance applications alongside binding offtake
negotiations to establish pricing certainty and support project financing.
Taken together, the PFS provides CMG with a clear, well supported technical and
financial foundation to progress toward a Definitive Feasibility Study (“DFS”) and Final
Investment Decision (“FID”).
MINERAL RESOURCE ESTIMATE
The Lindfield deposit is hosted in the Toolebuc Formation, a laterally continuous
Cretaceous marine sequence in the Carpentaria Basin. The deposit is sub-horizontal,
shallow (sub-cropping to ~30 m depth) and geologically low-risk.
The Mineral Resource Estimate (“MRE”) set out in Table 1 below. The MRE is 713 Mt at
0.32% V₂O₅ and 130 g/t Mo, which includes an Indicated Mineral Resource of 491 Mt at
0.32% V₂O₅ and an Inferred Mineral Resource of 222 Mt at 0.31% V₂O₅.2
In the Toolebuc Formation, Vanadium is contained in both the fresh and weathered
domains. Weathered Domain Mineral Resources exhibit less complex and lower-cost
metallurgical processing. The PFS focused on Vanadium Pentoxide extraction from the
weathered domains. The Lindfield MRE and geological block model includes definition
of the fresh to weathered transition. For the PFS mine planning and open-pit
configuration the pit floor cut-off was limited to the base of the weathered domains.
2
Refer to ASX Announcement dated 10 May 2024 entitled “Significant Increase to Lindfield
Project Mineral Resource Estimate Following Recent Drilling Campaign”.
4
Table 1 - Mineral Resource Summary3
Resource
Category
Domain Mass (Mt) V2O5 (wt%) Mo (g/t)
Measured Weathered - - -
Measured Fresh - - -
Indicated Weathered 261 0.30 110
Indicated Fresh 230 0.34 160
Inferred Weathered 61 0.32 110
Inferred Fresh 161 0.31 150
Total 713 0.32 130
Table 2 summarises the weathered Mineral Resources by confidence classification.
The weathered Mineral Resource comprises 80% indicated and 20% inferred.
Table 2 - Mineral Resources - Weathered Subset
Resource
Category
Domain Mass (Mt) V2O5 (wt%) Mo (g/t)
Measured Weathered - - -
Indicated Weathered 261 0.30 110
Inferred Weathered 61 0.32 110
Total Weathered 322 0.31 110
Table 3 Summarises the further explores the weathered Mineral Resources by
stratigraphic horizon, illustrating that the highest V2O5 grade is in the TLBB followed by
TLBD, and the highest Mo grade is in TLBD followed by TLBA.
3
The Company notes that approximately 91 Mt (12%) of the MRE is overlain by constrained land associated with the
former MDL522. Of this, 20Mt or 22% of the scheduled Mineralised Material within the Lindfield mining schedule is also
constrained. The company is working with the Department of Natural Resources and Mine Manufacturing and Regional
and Rural Development (“DNRMMRRD”) on a resolution.
5
Table 3 - Mineral Resources - Weathered Domain by Stratigraphic Horizon
Resource
Category
Domain Mass (Mt) V2O5 (wt%) Mo (g/t)
TLBA Weathered 212 0.22 70
TLBB Weathered 78 0.50 168
TLBD Weathered 33 0.40 184
Total Weathered 322 0.31 105
Figure 1 illustrates the Stratigraphic style of the Toolebuc Formation mineralisation. A
sedimentary deposit, all five units TLBA, TLBB, TLBC, TLBD and TLBE roll up and down
together, with minor variability in unit thickness, and negligible unmineralised
interburden material. At times, all units lay above the Base of Weathering (“BoW”) and
are therefore weathered resources, and vice versa below the BoW and are fresh.
Figure 2 is a section derived from the northern area of the target mineralised zone,
during preliminary mine economic evaluation. The section shows a grid with vertical
increments of 5m, the topographical surface, the roof and floor of mineralised units
TLBA and TLBB, as well as the BoW. What is also illustrated is;
• The shallow nature of the BoW, maximum 20m
• The increase in grade with depth in both units
• The mining block that defines the pit limit is impacted by a combination of rising
strip ratio and loss of the higher-grade material as the BoW truncates the TLBB.
Figure 1 - Representative Cross-Section Lindfield Vanadium Project (Source: Fig 3-10, PFS, Jul 2026, CMG)
6
Figure 2 - Representative Section - Grade, Strip Ratio, Economic Limit
The Mineralised Material used in the PFS was derived from the Weathered Mineral
Resource using a strip ratio and section method under the following constraints;
• Exclude all fresh and transition mineralised material
• 15m EPM boundary standoff at surface battered at 37 degrees to the BoW
• Limit TLBA resources by the lower 1.5m, directly above the TLBB
• Applied a strip ratio cutoff at 3:1
The impact of this mineralised material target is illustrated in Figure 3 below. The
target resources have very tight contours to most of the eastern boundary as the
Toolebuc Formation dips away due to faulting along this side. On the west, the
resource is truncated by the EPM boundary. Variability analysis at lower and higher
strip ratios caused little change to this target mineralised material area of the mineral
resource. In the north and south where the Toolebuc dips more gently, the strip ratio
cut off at 3:1 created the mining area illustrated in Figure 4 and blocked out for mine
scheduling accordingly.
7
Figure 3 - Strip Ratio Contours
8
Figure 4 - Lindfield Mining Block Sequence, including relevant proportions of the EMMM categorised as
Inferred and Indicated Minerals Resources
9
The subset of the Mineral Resource Estimate (MRE) used for mine scheduling in this
PFS, (the EMMM) are summarised below in Table 4 – Summary of total MRE Weathered
Domain Mineralised Material and the Economically Mineable Mineralised Material. The
95Mt at 0.41% V2O5 and 152g/t Mo represents just 13% of the April 2024 reported MRE
tonnage and 30% of the Weathered Mineral Resources portion of that same report
Table 4 – Summary of total MRE Weathered Domain Mineralised Material and the Economically Mineable
Mineralised Material subset of the MRE Weathered Domain Mineralised Material, being the PFS ROM Feed
material
Resource
Category
Domain
Mass (Mt) V2O5 (wt%) Mo (g/t)
MRE EMMM4
MRE EMMM MRE EMMM
TLBA Weathered 212 24.3 0.22 0.27 70 83
TLBB Weathered 78 46.2 0.50 0.50 168 173
TLBD Weathered 33 24.5 0.40 0.39 184 174
Total Weathered 323 95.0 0.31 0.41 105 152
The EMMM (See Table 4) is the ROM feed material in this PFS and includes both
Indicated and Inferred Resources. An Ore Reserve estimate has not been prepared at
PFS stage as, at this stage, information is insufficient to support the estimation of an
Ore Reserve.
The relevant proportions of the (Ore Reserve and) Mineral Resources underpinning the
mine plan and Production Target are set out in Table 5, Figure 5 and Figure 4
Table 5 – Economically Mineable Mineralised Material Classification of MRE
Classification Percentage of Production Target
Probable and Proven Ore Reserves 0%
Measured Mineral Resources 0%
Indicated Mineral Resources 89 Mt 94%
Inferred Mineral Resources 6 Mt 6%
4
EMMM – Economically Mineable Mineralised Material
10
Total 95 Mt 100%
PFS Cautionary Statement – Inferred Resources::
The Preliminary Feasibility Study referred to in this announcement has been
undertaken to consider a range of options for the technical and economic viability of
the Lindfield Vanadium Project. It is based on comprehensive technical and economic
assessments to provide the basis for development of the Modifying Factors used in
the financial analysis. The technical and economic assessments have not been
applied to support the estimation of ore reserves. Further evaluation work and
appropriate studies are required before CMG will be in a position to estimate any ore
reserves. Further evaluation work and appropriate studies are required before CMG
will be in a position to estimate any ore reserves or to provide assurance of any
development case.
The Preliminary Feasibility Study is based on the material assumption outlined below.
These include assumptions about the availability of funding. While CMG considers all
the material assumptions to be based on reasonable grounds, there is no certainty
that thy will prove to be correct or that the range of outcomes indicated by the
Preliminary Feasibility Study will be achieved.
To achieve the range of outcomes indicated in the Preliminary Feasibility Study,
additional funding will be required. CMG has a supportive shareholder base and has
successfully raised capital to progress the development in the past. CMG could also
potentially quality for funding from the Northern Australian Infrastructure Fund (NAIF),
National Reconstruction Fund (NRF), Export Finance Australia (EFA), the Clean Energy
Finance Corporation (CEFC), and with appropriate project credentials, source debt
funding through applicable sources. Investor should note that there is no certainty
that CMG will be able to raise that amount of funding when needed. It is also possible
that such funding may only be available on terms that may be dilutive to or otherwise
affect the value of CMG’s existing shares.
It is possible that CMG could pursue other ‘value realisation’ strategies such as a sale,
partial sale or joint venture of the Project. If it does, this could materially reduce CMG
proportionate ownership of the Project.
Given the uncertainties involved, investors should not make any investment decisions
based solely on the results of the Preliminary Feasibility Study.
11
Figure 5 - Production EMMM in relevant proportions of Inferred and Indicated Resources.
Cautionary Statement – Production Targets Inferred Resources: The Production
Target includes 94% Indicated Resource and 6% Inferred Mineral Resources. There is a
low level of geological confidence associated with Inferred Mineral Resources and
there is no certainty that further exploration work will result in the determination of
Indicated Mineral Resources or that the Production Target itself will be realised. The
production targets have been prepared by a Competent Person in accordance with
the requirements in Appendix 5A (JORC Code 2012).
PROJECT LAYOUT
Figure 6 outlines the current project layout concept that informed the PFS. The
resource is located in the northern portion of Lindfield EPM27872, with a conceptual
Mining Lease boundary placed around it. South of the defined mineral resource area is
an indicative location for the proposed mining infrastructure.
At the southern end of EPM27872 are the Townsville to Mount Isa railway line and the
Flinders Highway. It is currently proposed to develop an access road from the Flinders
Highway to the project area, running along the boundaries between landholders to
minimise impacts on farming operations.
The resource area is traversed by two stock routes, Punchbowl Road and Infrastructure
ML100245. The council quarry, known as the Lindfield 3 Pit Supply Zone, is expected to
be consumed by the open-cut mine at some point during development. These
matters will be addressed through stakeholder negotiations, which CMG is confident
can be resolved.
-
0.2
0.4
0.6
0.8
1.0
1.2
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Strip
Ratio
(t/t)
Tonnage
Material Movement (Mt)
ROM Feed Indicated ROM Feed Inferred Stockpile TLBA Stockpile TLBD Waste
12
Figure 6 - Project Layout
13
ASSESSMENT OF MODIFYING FACTORS AND KEY ASSUMPTIONS
MINING
Lindfield will be mined using a conventional open pit method suited to its shallow, flat-
lying and weakly consolidated ore body. A standard diesel truck and excavator fleet
will mine both mineralised material and waste without drill and blast, simplifying
operations and reducing cost relative to a typical hard rock mine. The mine will
employ standard small (80-100t) excavators and associated haul trucks and ancillary
mobile equipment. The mine will operate on a reduced roster 2-3 panel, 4-6 days per
week over the mine life due to the relatively small mining quantities.
The mining sequence is shown in Figure 8. The mining operation is designed to exploit
the lowest strip-ratio material first, while also providing operational redundancy
through the use of two working faces. Mining commences in Lode 1, strip 25 (L1_25),
and Lode 1, strip 13 (L1_13). The first face continues south to the end of Lode 1,
progresses through Lode 3, and then moves to Lode 2, working from south to north. The
second face proceeds south from L1_13 to L1_24, after which it returns to L1_12 and
works north to the northern extent of Lode 1.
Waste will initially be placed in a limited out of pit dump while early mining voids are
established, transitioning to a consistent in-pit dumping regime for the remainder of
mine life, with progressive rehabilitation maintained close behind the advancing
mining front. Lower cost alternatives, including scraper and dozer-push mining, will be
assessed further during the Definitive Feasibility Study.
In order to optimise production of V₂O₅ early in the mine life, the mining sequence has
been planned as follows;
• Strip and stockpile topsoil;
• Excavate overburden above the TLBA unit;
o The upper TLBA is deemed low grade and will be excavated along with
the overburden material above;
• Mine lower TLBA and stockpile;
• Mine the full TLBB in flitches and haul to the process plant, minimizing rehandle
and optimizing direct feed;
• If present, mine and waste the TLBC;
• Mine and stockpile the TLBD;
• When the TLBB is exhausted, reclaim the TLBA and TLBD is series and/or in
parallel, subject to grade control data and haul to the process plant.
Figure 7 summarises the mining quantities over the mine life. The strip ratio remains
under 1.6 : 1 throughout the mine life.
14
Figure 7 - Material Movement tonnages, Strip Ratio (SR)
Figure 9 illustrates the consistent delivery of 3Mt ROM to the process plant over the 31
years of mine life. Due to the high grade and recovery rate of the TLBB, annual V2O5
production is forecast to range between 10,000 – 12,000 t per annum for the initial 16
years. TLBA has a low feed grade but higher recovery rates. TLBD has a higher grade,
and further studies are required to confirm its recovery rate. Accordingly, these two
mineralised material units are forecast to produce approximately 6,000 t per annum
for the remaining 16 years of the mine life.
-
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Strip
Ratio
(t/t)
Tonnage
Material Movement (Mt)
Mine TLBB Reclaim TLBA Reclaim TLBD Stockpile TLBA
Stockpile TLBD Mine Overburden Mine TLBC (Waste) Cum SR
15
Figure 8 - Mining Sequence
16
Figure 9 - Feed material and Product Tonnes
MINERAL PROCESSING AND METALLURGY
Figure 10 - Indicative layout Lindfield Mine and processing infrastructure
A comprehensive metallurgical test work program has been undertaken to support
development of the Lindfield Vanadium processing flowsheet and provide the design
inputs required for the preliminary process design and metallurgical mass balance.
Test work was primarily conducted by Brisbane Metallurgical Laboratory (BML) under
multiple laboratory scopes of work (SOW#1 to SOW#8) and covered the principal unit
operations of the proposed processing circuit, including scrubbing, screening, hydro-
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35
Ore
Processed
(k
tonnes)
Period (Yr)
3Mtpa - Feed by Mineralised Unit & Total Product tonnes (kt)
TBLA Ore TBLB Ore TBLD Ore Total Recovered Pentoxide - 3Mtpa B, A, D
17
cyclone classification, flotation, leaching, solvent extraction, ion exchange,
precipitation, and solid-liquid separation.
The flowsheet has been designed to minimise new water demand and reduce
environmental impact where possible. The flowsheet is broken into two main sections,
physical separation (front end) and chemical processing (back end). The front end
includes scrubbing, screening, cyclones and flotation which are aimed at rejecting as
much gangue as possible with minimal value loss to upgrade the vanadium and
reduce the volume feeding into the chemical part of the flowsheet. The back end
includes leach, solvent extraction (“SX”), ion exchange (“IX”) and precipitation.
The physical separation processes have been tested at pilot scale and were used to
generate the material for much of the later testwork on the chemical section of the
flowsheet. Rejects from scrubbing, screening and cycloning are chemical free and
able to be returned to the pit for progressive rehabilitation. This would commence
once waste material placement within the pit had reached a steady-state condition.
Figure 11, Figure 12 and Figure 13 show the pilot scale scrubbing of the TLBA horizon
material. TLBB horizon was tested in the same program. Figure 14, Figure 15 and Figure
16 show the cyclone and flotation pilot work. TLBD material pilot scale testing would be
set for the Definitive Feasibility Study.
From Left to right:
Figure 11 - Image 3: Intermediate (-8mm+2MM) reject material from scrubbing
Figure 12 - Image 2: Coarse (+8mm) reject material from scrubbing
Figure 13 - Image 1: Scrubbing TLBA Horizon material – drill core from the Lindfield Project
18
From Left to right:
Figure 14 - Image 6: Pilot flotation testwork
Figure 15 - Image 5: Cyclone overflow and underflow samples from Pilot testwork
Figure 16 - Image 4: Pilot cyclone testwork on TLBB horizon
Extensive bench-scale test work was undertaken to assess a range of leaching
options, including roasting or microwaving ahead of leaching and alkaline leaching, to
determine whether total sulphuric acid consumption across the flowsheet could be
substantially reduced. At this stage, the most economic approach remains sulphuric
acid leaching supplemented with an oxidant, with no roasting required.
As outlined in the flowsheet described above, solvent extraction was selected to
separate vanadium and molybdenum from other elements in the leach liquor. A
number of reagents were tested to determine the required number of extraction
stages. Following solvent extraction, ion exchange has been selected as the preferred
processing route for molybdenum recovery. Both vanadium pentoxide and
molybdenum trioxide will then be precipitated using ammonium sulphate and
calcined to produce the final products.
Settling and filtration test work has been conducted on all relevant process streams to
support design calculations and reagent selection.
Opportunities for optimisation have been identified throughout the flowsheet and will
be tested during the Definitive Feasibility Study. Detailed planning for this work is
underway. The main focus of post PFS test work will be optimisation of flotation and
leach parameters, refinement of SX/IX and precipitation conditions, and pilot-scale
test work under the optimised operating conditions.
19
PROCESS ENGINEERING
CMG engaged Sedgman Prudentia, a specialist minerals processing engineering firm,
to independently develop the process design, mass and energy balance, and capital
cost estimate underpinning the Lindfield Project's Pre-Feasibility Study. This
engineering work forms the technical backbone of the study, translating metallurgical
test work results into a defined plant design capable of supporting reliable capital and
operating cost estimation. Water management was included in the design principles
with a focus on minimising fresh raw water consumption, reducing long-term
environmental impact, and maximising internal recycling while maintaining process
stability.
Sedgman Prudentia's scope centred on three linked deliverables.
1. A mass and energy balance was developed from CMG's metallurgical test work
program, establishing the process flows, reagent consumption rates, water
recycle requirements and energy demand across each stage of the flowsheet,
from beneficiation and flotation through to leaching, solvent extraction and
product recovery.
2. Preliminary equipment sizing and a corresponding plant layout (Figure 9),
covering major processing infrastructure across the 1, 3 and 4 Mtpa
development cases, including the scrubber, flotation cells, leach tanks, solid
liquid separation, solvent extraction and precipitation circuits.
3. Capital cost estimate using its proprietary Esy cost modelling system, which
integrates vendor equipment quotations, installation factors, construction
labour costs and project allowances into a single, auditable cost build-up.
The beneficiation circuit is designed to maximise gangue rejection ahead of reagent
addition, preserve vanadium recovery, maximise internal water recycling, and
maintain segregation between untreated reject and chemically treated process
streams. Reject material therefore remains chemically uncontaminated and suitable
for return to mine for rehabilitation and controlled civil infrastructure use.
The leach circuit is designed to maximise vanadium recovery while managing acid
consumption, heat integration, and scaling risks prior to solvent extraction. Integrated
recycles are utilised in all stages to maximise recovery and minimise reagent use and
metal losses.
The solvent extraction circuit is configured to maximise vanadium and molybdenum
recovery, control impurity build-up in recycle streams, maintain stable organic phase
chemistry and deliver consistent feed to the downstream precipitation stages.
The precipitation and calcination area converts dissolved vanadium and molybdenum
from the SX strip solution into marketable oxide products. Molybdenum is separated
and processed separately as it is a significant detrimental contaminant in the
downstream production of vanadium electrolyte The precipitation stages are
designed to recover vanadium as vanadium pentoxide (V2O5) and molybdenum as
molybdenum trioxide.
20
The tailings neutralisation circuit consolidates acidic and alkaline process effluents
into a single conditioned stream suitable for disposal to the Tailings Storage Facility
(TSF). The circuit is designed to manage residual acidity, dissolved impurities and
suspended solids while supporting the overall site water balance control.
Where possible, major mechanical equipment costs were based on budget quotations
obtained directly from vendors; remaining items were estimated using benchmark
data drawn from comparable mineral processing operations and Sedgman
Prudentia's historical project database. This combination of vendor sourced pricing
and independently benchmarked data provides a capital cost estimate consistent
with the level of engineering definition appropriate to a PFS, while identifying the
specific areas including downstream ammonium metavanadate precipitation and
product recovery that will be advanced through further engineering during the
Definitive Feasibility Study.
OTHER MODIFYING FACTORS
• Infrastructure - Water, power and access
A strategic review of the water catchment in the region, including the Julia Creek and
Richmond areas, was undertaken by Sunwater Limited (Sunwater) with support from a
Critical Minerals Water Reference Group (“CMWRG”) established for the Project. The
CMWRG comprised representatives from the Office of the Coordinator-General, the
Department of Natural Resources and Mines, Manufacturing, and Regional and Rural
Development, the Department of Local Government, Water and Volunteers, and
Queensland Treasury. The “Strategic Assessment into the Julia Creek | Richmond CMZ5
Water Delivery Options Stage 1 Report” recommended that the Critical Minerals Zone
(CMZ) should be supported by both surface water harvesting and underground water
supply.
For the Lindfield Project, both water sources are likely to be available. The PFS identified
Alick Creek, an Order 7 stream, flowing through EMP27872, as well as the presence of
the Great Artesian Basin (GAB) below EPM27872 at depths between 250-400m.
Development of these water supply sources independently has been the basis of the
water supply strategy for Lindfield and will be further refined under DFS. Should a
coordinated industry approach to water supply be developed by government and
industry stakeholders, this would be considered a potential upside case.
The Lindfield power supply study was assessed and optimised over the study period.
As per CMG’s announcement in October 2025,6
it was as determined that a hybrid
power generation solution combining solar PV, wind generation, battery storage and
5
CMZ – Critical Minerals Zone
6
Refer to CMG’s ASX announcement dated 2 October 2025 entitled “Lindfield Vanadium Project
Power Supply Study Completed”.
21
diesel generator backup was the most optimal solution. Further evaluation during the
study improved the renewable penetration level to ~95% renewable power and
increased the certainty of the economics, resulting in an estimated power cost of
approximately $0.15/kWh under a power purchase agreement (“PPA”) to be
negotiated and finalised at a later stage.