Annual Report to shareholders
Released
Released
Announcement PDF
Annual
Report
Leading the way in the
renewable energy transition
25
Our
Reporting Suite
Annual
Report
25
Leading the way in the
renewable energy transition
Annual Report
ESG
Report
Leading the way in the
renewable energy transition
ESG Report
25
Acknowledgement
of Country
Critical Minerals Group acknowledges the Traditional
Custodians of the lands on which we operate.
We recognise the Miajabi(Mayi-Yapi) and Mycoolon people
and the Mayi and Mitakoodi people who are the Traditional
Owners of the land on which our tenements are located;
the Yugambeh People, Traditional Owners of the Logan
City region; and the Turrbal and Jagera Peoples, Traditional
Owners of the Brisbane region.
We pay our respects to Elders past, present and emerging.
Table of
Contents
Introduction4
Letter from the Chair
4
Company Overview
5
Chief Executive Officer’s Update
CMG’s Evolution
Market to Mine Strategy
Company Structure & Business Model
Case Study
6
6
10
12
14
Directors’ Report
Remuneration Report
16
28
Financial Report
Auditor’s Report
35
56
2025 Achievements
$4.8m
in grants combined
from all levels of
government
Exploration permits
for Lindfield North
and Lara Downs
Granted
Vanadium Electrolyte
Manufacturing Facility
Site secured &
FEED stage complete
Awarded
Lindfield Pilot plant test work
BESS business strategy
Commenced
Established
Development of
project pipeline for
Strategic partnerships for
energy solution supply chain
BESS Business
Established
Chief Operating Officer &
Chief Financial Officer
Appointed
$5m
Successfully raised
Partnerships
Annual Report FY25
3
Letter from
the Chair
Dear Shareholders,
It is my pleasure to present the Critical Minerals Group (CMG) Annual Report for the 2025 financial year. This
has been a year of significant progress for the company, marked by strategic development and continued
momentum across operational activities.
Our vision is clear: to establish an integrated vanadium supply chain to support the delivery of Vanadium
Flow Battery (VFB) energy storage solutions. Over the last 12 months, under the leadership of CEO Scott
Winter, we advanced this vision with measurable achievements. From resource development at our
Lindfield Project, to finalising the design and front end engineering design (FEED) stage of our Vanadium
Electrolyte Facility in Logan, and progressing the development of our downstream energy storage business.
These milestones strengthen our ability to deliver secure, scalable, and sustainable energy solutions to the
market, positioning CMG as a future leader in the global energy storage sector.
This year has also underscored the importance of strategic partnerships in accelerating our pathway.
Our collaboration with Idemitsu, together with strong engagement with both the Queensland and Federal
Governments, provides validation of our strategy and creates new opportunities for growth.
Importantly, CMG has also proactively advanced relationships with global battery leaders, technology
partners, and investment stakeholders to support the successful delivery of our downstream VFB energy
storage solution business.
These key relationships are a cornerstone of CMG’s approach. Leveraging expertise, resources, and
alignment with national energy objectives to deliver long-term value for our shareholders and stakeholders,
while predicting and meeting the demands of an incredibly dynamic energy market.
Sustainability remains at the core of our operations. We are committed to supporting the global energy
transition while maintaining high standards of environmental stewardship, safety, and community
engagement. The initiatives undertaken in FY25 reflect our dedication to responsible growth, and we remain
focused on creating shared value across the regions where we operate.
Looking ahead, FY26 promises to be another defining year for CMG. With a strengthened foundation, a
growing pipeline of opportunities, and an experienced team, we are well positioned to capture the benefits
of a rapidly expanding global market for vanadium-based energy solutions.
On behalf of the Board, I extend my gratitude to the management team for their commitment and
leadership, and to our shareholders for their ongoing trust and support. Together, we are building a
business of scale and impact, one that will play a pivotal role in shaping Australia’s energy future.
Yours sincerely,
Alan Broome, AM
Chair
4
criticalmineralsgroup.com
Company
Overview
Purpose
Vision
Strategy
To support global communities through an energy
transition that will deliver a more sustainable and
responsible future.
We will be known as the leading provider of high-quality
reliable energy storage solutions delivering robust
returns through our fully integrated and controlled
vanadiumn supply chain.
Upstream supply security
ᴑ Vanadium pentoxide (V2O5) production
ᴑ Vanadium electrolyte (VE) manufacturing
ᴑ Extract value added by-products
Downstream Value Creation
ᴑ Vanadium Battery Energy Storage Systems (BESS) solutions
ᴑ Integrated supply chain
ᴑ Commercial and industrial market
Sustainable Delivery
ᴑ Integrating ESG in business deliverables
ᴑ Vanadium BESS powering CMG
FY25
Objectives
ᴑ Traditional Owners involvement
CMG has achieved its FY25 objectives of:
ᴑ Implemented a strategy to participate in the end to
end Vanadium Flow Battery (VFB) Supply chain
ᴑ Commenced the PFS for the Lindfield project
including pilot plant testing
ᴑ Developed a pathway to vanadium electrolyte
manufacturing
FY26
Objectives
ᴑ Established an ESG framework and an ongoing
reporting structure for key ESG initiatives
ᴑ Continue establishing a pipeline of VFB
potential projects
ᴑ Generate early cashflow from the VFB energy
storage solutions
ᴑ Complete the PFS for the Lindfield Project and
associated pilot test work
ᴑ Complete vanadium electrolyte manufacturing
capability and pathway for growth
Annual Report FY25
5
Chief Executive
Officer’s Update
2024-2025: CMG’s Evolution
The strategy and brand launch in August 24 was a great
success with support from shareholders, government
departments, community and technical partners. When the
team reflected on the major value driving factors influencing
the vanadium flow battery (VFB) market it became clear that
CMG needed to be involved across the vanadium supply
chain and not only the development of the Lindfield mine.
This would require CMG to participate in the midstream
manufacturing of the active material which is vanadium
electrolyte as well as understanding the energy market and
developing a capability to deliver energy storage solutions
using vanadium flow batteries. The strategy centred around
creating demand and offtake of longer duration energy
storage which would lead to the offtake of vanadium
electrolyte and in turn vanadium pentoxide. In support of this
strategy, CMG unveiled a brand that it felt truly reflected what
the company was aiming to achieve across the vanadium
supply chain.
The ongoing development of the Lindfield vanadium project
has been rewarding. A range of environmental studies were
started and the team had early discussions with the local
Traditional Owners on country, as well as the Julia Creek and
McKinlay shire community. The pre-feasibility study kicked
off with Sedgman Prudentia and quickly resolved many key
technical elements. We are excited that the metallurgical
test work evolved to a point where we were confident to
commence Pilot Plant testing. The team also successfully
investigated alternate vanadium process flow sheets to
improve recovery and reduce capital and operating costs.
Establishing the mid stream vanadium electrolyte business
was a terrific achievement. CMG found both the QLD State
and federal governments to be aligned with the strategy
and supportive of the investment in the downstream
manufacturing of QLD won raw materials. CMG was fortunate
enough to secure a $2 million grant from the QLD Treasury
in support of the development of a vanadium electrolyte
manufacturing plant located in Logan QLD, which has been
critical in the funding of the plant and its development.
We are encouraged by the engagement we have received
from vanadium battery suppliers since embarking on this
development and see offtake agreements as a natural next
step as the plant is commissioned into steady state operations.
Embarking on the development of the energy storage
business was an exciting and rewarding journey for the
team. A significant amount of time and effort was spent in
understanding where VFB would best support the market,
engaging and securing the specific partners required to
support CMG’s business and identifying customers with
potential VFB installation projects. We see an increasing
demand in the National Energy Market (NEM) and Wholesale
Electricity Market (WEM) for long duration energy storage
suited to VFB’s and see FY26 as another growth year.
CMG has made significant inroads in the upstream
Lindfield development, midstream vanadium electrolyte
manufacturing and downstream energy storage solutions.
We see this will bring forward cash flow into 2026 and allow
CMG to make growth and capital investment decisions
based on tangible market demand.
Annual Installed VRFB Utility-Scale and Commercial and
Industrial Battery Deployment Energy Capacity by Region,
All Application Segments, World Markets: 2022-2031
35,000
30,000
25,000
20,000
MWh
It is with great pride that we present to you the year that was
2025 and share with you the significant progress the team
has made. FY25 was a year of growth and evolution in Critical
Minerals Group (CMG) as we communicated our business
strategy at a brand launch earlier in the year and made it
very clear what the areas of focus were for CMG.
15,000
10,000
5,000
0
2022
2023
2024
2025
2026
2027
2028
2029 2030
North America
Latin America
Asia Pacific
Eastern Europe
Western Europe
Middle East
Source: Guidehouse Insights, Vanadium Redox Flow Batteries:
Identifiying Market Opportunities and Enablers, 2022
6
criticalmineralsgroup.com
2031
Africa
The Energy Market: Demand and Dynamics
The energy sector is in constant evolution as the energy
transition rolls out across the nation and the globe. The
changes occurring in the marketplace affect CMG in a
positive way. To ensure CMG is well positioned to take
advantage of these opportunities the company is continually
assessing and reviewing its strategy and key focus areas.
however do not provide energy overnight and through the
morning peak. The data shows that we are approaching 80%
renewables consumption during the daylight hours, however
the lack of long duration battery storage means we revert
to more than 80% coal/gas fired power overnight. VFBs are a
proven, readily available technology that can shift the excess
renewables energy generated during the daylight hours to
significantly reduce coal/gas consumption and hence overall
energy costs through the entire night and morning peak .
With CMG’s vanadium targeted at the vanadium flow battery
market, the main area of focus is the domestic energy
market and in particular the energy storage demand. With
a lens on Australia; the renewable energy rollout across the
nation has been occurring for over ten years with major
growth in rooftop solar as well as larger solar and wind
investments occurring in regional and remote areas. The
initial investments focussed on renewable energy without
backup storage, however in recent years a significant
opportunity in peak time energy trading in the morning and
evening have seen increased investment and installation of
short duration batteries to take advantage of high returns.
Long duration vanadium flow batteries can support the
energy transition, and AEMO has recognised this. Quarterly
reporting from the Australian regulator AEMO indicates a
recent trend towards longer duration energy storage needs
in the NEM and WEM. Long term forecasts indicate that
by 2050, 88% of energy use will come from long duration
energy storage. In the short term major energy “gentailer’s”
across the nation are issuing tenders for energy storage with
duration specifications greater than 10 hours, which is ideally
suited to vanadium flow batteries.
These batteries are short in duration with up to two hours
in capacity and assist with high energy demand periods
The graphs below indicate at midday, renewable energy utilisation is rapidly increasing and approaching the government
target of 80%, however lack of long duration energy storage results in a sharp drop overnight e.g. at 6pm.
Quarterly supply at 12:00
Quarterly supply at 12:00
Q1
Feb
100.00%
Q1
Feb
Q2
June
Q2
June
Q4
October
Q4
October
Chart Title
Quarterly
supply at 18:00
Chart Title
Quarterly
supply at 18:00
Q1
Feb
Q1
Feb
Q2
June
Q2
June
Q4
October
Q4
October
100.00%
Year-on-year – this is not changing
BESS
Rooftop
Rooftop
Hydro
Gas
Gas
2024
2023
2024
2023
20212022
2022
20192020
20202021
20252019
20242025
2023
2022
20232024
2022
2021
Hydro
2021
2019
2020
2020
2025
2019
2025
20232023
Solar
Solar
20242024
20212021
20222022
2019
2024
2024
2022
Wind
Wind
2023
2023
20212020
20222021
20192025
Other
Other
20202019
20252024
20242023
2021
2022
2022
DispLoad
BESS
DispLoad
Source: Greenview Analysis Jul 2025
2023
2019
2020
2021
2025
20192024
2020
20252023
20232021
20242022
20212019
2020
2019
20222020
0.00%
0.00%
2019
20.00%
20.00%
20202020
40.00%
40.00%
Some year-on-year
improvement
Year-on-year – this is not changing
% of Total GWh
% of Total GWh
60.00%
60.00%
Some year-on-year
improvement
80.00%
80.00%
Coal
Coal
Annual Report FY25
7
Chief Executive
Officer’s Update
As the focus on energy storage grows the focus on capital
and operating costs increases and solutions are driven to
be more efficient and cheaper. This is occuring across all
enegy storage categories and in particular VFB’s as the
number of installations increase and supply chains become
more robust. In comparison this trend has not occurred with
domestic pumped hydro energy projects as infrastructure
costs increase and approvals are delayed. Vanadium flow
batteries are fast becoming more competitive on a capital
installation basis and surging ahead on the levelised cost of
storage (LCOS).
Like Australia, many other countries are seeing the benefits
of vanadium flow batteries and the installations of this type
of battery increasing. China and Asia lead the way with VFB
installations of up to 1GWh commissioned in 2025, with Japan,
USA, Europe, and the UK installing VFB’s on a regular basis.
CMG’s progress in the supply chain has not gone unnoticed
in the sector both domestically and internationally. With
major VFB suppliers and manufacturers based offshore and
noticing the opportunity in Australia, CMG is experiencing
significantly increased activity and engagement from
suppliers and potential customers.
There is significantly higher curtailment of solar and wind
generators caused by transmission and economic issues
resulting in many generators augmenting their investments
with energy storage solutions. Vanadium flow batteries solve
this issue by integrating the renewable generator with the
battery to create a hybrid renewable solution with increased
flexibility in energy distribution.
With the positive trends in government policy, regulator
focus, decreasing costs, increased VFB installations,
improved supplier technology support and clarity on VFB
domestic opportunities, CMG saw the opportunity for
significant domestic growth in VFB installations. With a
growing domestic VFB installation market CMG saw this
as the opportunity to underpin the establishment of the
vanadium supply chain and in particular the development
of both the vanadium electrolyte manufacturing and the
production of vanadium pentoxide.
A recent report from AEMO targeted at the transmission and
distribution network across the NEM highlighted a growing
infrastructure issue and that significant investment was
required to upgrade poles and wires to distribute renewable
energy generation.
49GW/646GWh
of dispatchable storage required by 2050
to support 58GW Solar and 69GW wind.
88%
of all long duration energy
storage (LDES) by 2050.
8
criticalmineralsgroup.com
Ref: AEMO, 2024 Integrated System Plan for the National Electricity Market
What is the Opportunity for
Vanadium Flow Batteries?
Lifespan
25+ years
20,000+ cycles
Scalability
Electrolyte
volume
Price
Low LCOS
Med-Long
Duration
Best suited to
6+ hours
Sustainability
Battery 98%
recyclable
Recyclability
Electrolyte
reusable
Nil Degredation
Vanadium
electrolyte does
not degrade
Safety
Non-flammable
and highly stable
Energy & Power Density
Small and large grid applications
The Future is Hybridisation
CMG has clearly defined its target customers and
an achievable growth pathway. The target customer
applications achieve:
ᴑ Enhanced economic
efficiency of renewable
energy
ᴑ Load balancing and
enhancing grid resilience
Substation
Mine
Community
Solar PV
Datacentre
ᴑ Power security and
reliability
ᴑ Continuous Power supply
ᴑ Lowering diesel usage
and associated carbon
emissions
Chief Executive
Officer’s Update
Market to Mine Strategy
Pentoxide production
Electrolyte manufacturing
Vanadium mining
and processing
Electrolyte
manufacture
Extraction
Electrolyte manufacture
V2O5 processing
Quality testing
Transport and logistics
Storage and logistics
Upstream demand dictated by BESS project pipeline
Upstream supply security
10
Downstream value crea
Vanadium pentoxide (V2O5) production
Vanadium BESS solutions
Vanadium electrolyte (VE) manufacturing
Integrated supply chain
By-products
Commercial and industr
criticalmineralsgroup.com
Through the development of an internal capability to develop energy storage
solutions using vanadium flow batteries and focussing on delivering those
solutions to customers, CMG enhanced the overall strategy.
CMG’s model integrates upstream (mining), midstream (vanadium electrolyte production), and downstream (energy
storage solutions) to create a complete vanadium supply chain.
The market-to-mine strategy ensures a balanced supply-demand dynamic and optimal pricing. Prioritising early cash flow
and risk mitigation, we protect shareholder investments while enabling sustainable demand-led growth.
Battery Energy Storage System solutions
ation
Vanadium Flow Battery storage solutions
Developer services
Technical/financial feasibility
Battery, hardware and software supply
Microgrid development
(rural, remote)
EPC management
Heavy industry and grid
scale development
Hybrid development
Operations and maintenance
Market-to-mine strategy
Sustainable delivery
s
Integrating ESG in business deliverables
Vanadium BESS powering CMG
rial market
Traditional Owner involvement
Annual Report FY25
11
Chief Executive
Officer’s Update
Company Structure & Business Model
CMG is structured in a way to capture the value in each of the different
business streams, upstream – Lindfield vanadium project, Midstream vanadium electrolyte and downstream - energy storage solutions. This
allows for flexibility and the growth of individual business streams to be
organic and defined by the market dynamics they operate within.
ᴑ In establishing the energy storage solutions business,
manages a range of EPC contractors that carry out the
deliver an installed vanadium flow battery. The elements
civil, electrical, controls and remaining engineering work.
of the supply chain required to deliver an operating
vanadium flow battery are extensive and CMG has
formed strategic partnerships to give the capacity to
deliver reliable solutions.
ᴑ Project origination and customer engagement is
required to populate the pipeline of potential VFB
customers to match the attributes of the VFB and works
alongside to progress the opportunities. At this early
stage both the commercial agreements and funding
planning is carried out.
ᴑ CMG has both technical and commercial partners to
evaluate and analyse potential projects in order to define
a project scope. As the opportunity evolves to an agreed
project, the team with key partners develop the design
and operating principles of the energy storage asset.
ᴑ As each VFB project is unique the equipment required
differs between each project. CMG has a wide range
of supply relationships for vanadium electrolyte, wet
and dry vanadium flow batteries, PCS’s, transformers
and other balance of plant items. Control systems and
software to accompany the equipment is also delivered
through specific suppliers.
12
ᴑ In order to construct and deliver the installation CMG
CMG has established the building blocks necessary to
criticalmineralsgroup.com
ᴑ The operations and maintenance are the final
components of the supply chain and is an integrated
service between the original equipment manufacturer
and locally based service providers. Depending on the
project and customer requirements CMG supports the
VFB asset to the extent required.
The strategy to develop an integrated vanadium supply chain
in Australia to support the growing demand for long duration
energy storage is one that CMG is delivering against. The
approach brings cashflow into 2026 through the VFB energy
storage solution business. Initially third-party vanadium
electrolyte and vanadium flow batteries will be used to deliver
solutions until CMG’s vanadium electrolyte manufacturing
plant is able to supply VE into third party VFB’s.
Each project is being established through a separate
Special Purposes Vehicle under the energy storage solutions
business and funded accordingly. The commercial solutions
for customers range from a full turnkey delivered VFB that is
then owned by the customer to a leasing model where the
customer has a long term lease with regular payments for
either the whole or Vanadium electrolyte part of the VFB.
Downstream BESS solutions installation targets
CMG Plans to use the Lindfield V2O 5 production to manufacture vanadium electrolyte and then use this entire production in
vanadium battery installations.
chain production per annum
10,000t
of V2O5
68m litres
vanadium electrolyte
1.3 GWh
vanadium battery
storage capacity
CMG can be flexible with its commercial model
Asset lease/rent
Margin derived from
delivering project
related services
Design, procure, engineering,
procurement and construction
(EPC), operations and
maintenance (O&M)
Vanadium electrolyte
leasing/rent
The total battery solution
Customer engagement
Economic modelling
Project origination and
commercial agreements
Assessing battery size, duration, BMS
Battery management system,
energy management system
Project scoping studies
EPC management
Funding/PPA
Feasibility, demand forecasting,
risk analysis, equipment selection
Construction and delivery of asset
Funding options — ownership,
lease, finance
Technical design
Supply items
Operations & maintenance
Energy asset design, battery,
and PV
Vanadium electrolyte, vanadium
battery, solar panels, inverter
Ongoing maintenance of asset
Software supplier
Annual Report FY25
13
Chief Executive
Officer’s Update
Case Study
One 2MW battery, 16 MWhrs, 8hr storage capacity
A 2MW battery energy storage system (BESS) with an 8-hour
storage capacity can deliver 16MWh or 16,000 kWh of energy.
Using the assumptions in Table 1, CMG anticipate the following:
ᴑ If CMG produce its own pentoxide, the expected
internalised margin to the vanadium electrolyte business
is ~$0.70M, on a cost of production of ~$2.2M
ᴑ If CMG manufacture its own vanadium electrolyte, the
expected internalised margin to the BESS business is
~$1.1M, on an installed battery cost of ~$16M
ᴑ If CMG assembled and installed the battery, the
expected internalised margin to the BESS business is
~$1.4M on an installed battery cost of ~ $16M
ᴑ A fully integrated model would result in an internalised
margin of approximately $3.2M, against a total installed
battery cost of ~$16M.
Integrated solution benefits
By integrating a complete supply chain, CMG can increase
efficiency and scalability and leverage the advantages of
internalising cost margins.
Cost reduction
By optimising production and reducing reliance on
external suppliers, CMG is able to significantly lower costs
associated with battery supply.
Performance optimisation
Performance optimisation of CMG’s internalised process
allows for better control over the design and quality of
components, leading to improved battery efficiency.
Scalability
Opportunity for scale with streamlined production and a
fully integrated solution.
Assumptions
6.9l Vanadium Electrolyte
Table 1
Unit
*Internal
Purchase
Price
*CMG
Production
Cost
$/kg
~$25
~$18.6
$/kWh
~$182
~$145
$/kg
~$5.5
~$4.1
$/kWh
~$290
~$205
1kg Pentoxide
0.14 kWh
Pricing
Pentoxide
1l Vanadium
Electrolyte
0.02 kWh
Vanadium
Electrolyte
*VFB grade V2 O 5
One 2MW battery
(16 MWhrs,
8hr storage)
14
criticalmineralsgroup.com
$16M
“Queensland and Australia has an incredible
opportunity to take control of the vanadium supply
chain and drive power costs lower. From pentoxide
processing to electrolyte manufacturing and VFB
assembly and installation, establishing an end to
end supply chain positions Australia as a leader in
the growing global energy storage market and brings
us a step closer securing the long term benefits for
Australian industry, jobs and regional communities.”
William Scott Winter
CEO and Managing Director
Annual Report FY25
15
Directors’
Report
Contents
Review of Operations and Principle Activities
Group Projects
Environment, Social and Governance
Information on Directors
Remuneration Report
Directors’ Declaration
Auditor’s Independence Declaration
16
criticalmineralsgroup.com
17
20
22
24
28
33
34
Your directors present their report on Critical Minerals Group Limited (“the Company”) and its controlled entities (“the Group”),
for the financial year ended 30 June 2025 (FY25).
Directors and
Company Secretary
The names of the directors in office at any time during, or
since the end of, FY25 are:
Alan Broome, AM
William Scott Winter
Art Malone
Resigned 31 May 2025
Steven Kovac
Stuart McClure
Directors continue or were in office from the start of FY25 to
the date of this report unless otherwise stated.
Trudy Walsh was appointed joint Company Secretary with
effect from 20 June 2025.
Registered Office
The Company’s registered office and principal place of
business is:
Level 15
100 Edward Street Brisbane QLD 4000
The Company’s phone number and email address is:
Phone: (07) 3132 3504
Email: info@criticalmineralsgroup.com.au
Review of Operations and
Principle Activities
This Directors’ Report contains a review of the Group’s
operations, including information on exploration activity
and results, financial position, strategies, and projects of the
Group for FY25.
During FY25, the Company successfully completed two
entitlement offers of:
ᴑ 16,624,059 ordinary shares at $0.15 per share raising
$2.494 million before costs, and
ᴑ 18,506,971 ordinary shares at $0.135 per share raising
$2.498 million before costs
The Group’s financial position, financial performance, and
use of funds and changes of equity information for FY25
is provided in the financial statements that follows this
Directors’ Report.
The Group incurred a loss of $2,680,420 for FY25, resulting
from administration expenses, professional and consulting
fees and employee costs.
The Company, as an exploration entity, has no operating
revenue. The performance of the Group, in the Directors’
opinion, is based on the success of the exploration and
development activities and the acquisition of mining
interests by the Group.
The Company is pleased to provide an update on activities
completed during FY25.
The Company is an exploration and energy company
focussed on developing an end to end vanadium supply
chain to deliver vanadium flow battery energy storage
solutions. As part of its business model, CMG has developed
three distinct business segments: Upstream (Mining and
Vanadium Pentoxide Production), Mid Stream (Vanadium
Electrolyte manufacturing), and Downstream (VFB energy
storage solutions). During FY25, significant progress was
made across all of the business streams.
Upstream: Vanadium Pentoxide Production
The Company commenced a prefeasibility study into the
Lindfield Project in FY25, along with a series of environmental
studies for the Lindfield Project Environmental Impact
Statement (EIS).
The majority of the field studies were originally scheduled
for the March/April period however these were delayed due
to the substantial rain late in the season making access to
certain areas problematic.
Annual Report FY25
17
Directors’
Report
Review of Operations and Principle Activities (continued)
Applications for Coordinated Project Status and an EPBC
submission (Environment Protection and Biodiversity
Conservation Act) are also in the final stages of preparation.
Metallurgical testwork focussed on the completion of pilot
work for the beneficiation stages (scrubbing, screening,
cycloning) and flowsheet optimisation for flotation, leaching
and downstream operations. The pilot test work to date
was conducted on material sourced from twin holes
drilled in the 2023 drill program carried out at Lindfield.
The beneficiation testwork processed the material from
the A and B horizons separately to better understand the
differences in performance when tested on a larger scale.
The results indicated better performance than the original
bench scale tests, due to the pilot equipment being more
representative of the equipment likely to be installed in a
full-scale operation. The pilot work also tested single versus
two stage cyclone operation, opting for two-stage due to the
higher vanadium and molybdenum recoveries.
Subsequent bench scale flowshee
Share your feedback