Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
criticalmineralsgroup.com.au
(+61) 731 323 504
Level 15, 100 Edward St, Brisbane QLD 4000, Australia
info@criticalmineralsgroup.com.au
ASX Announcement
ASX: CMG
31 July 2026
Quarterly Activities Report & Appendix 5B for the period ending
30 June 2026
KEY HIGHLIGHTS
• CMG completed a Pre-Feasibility Study confirming a technically executable and
financially compelling critical minerals development.
o The study was for the Lindfield Vanadium Project, which included the
development of an integrated open-cut vanadium mine near Julia Creek
and a Vanadium Electrolyte (VE) manufacturing facility at Parkes in NSW.
• CMG is now advancing the Project from Pre-feasibility to Definitive Feasibility
with three priority workstreams identified to underpin that transition and assist in
achieving a Financial Investment Decision (FID) for the Lindfield Project and VE
facility:
o Mineral resource upgrade and completion of the metallurgical pilot plant
programme to confirm and improve vanadium recovery;
o securing long-term, competitively priced supply agreements for high
usage reagents (sulphuric acid and sodium hydroxide), which together
represent a significant proportion of processing operating costs; and
o advancing government concessional finance applications alongside
binding offtake negotiations to establish pricing certainty and support
project financing.
• CMG is in discussions regarding offtake of vanadium electrolyte to support
vanadium battery installations for data centre developments;
• CMG completed a successful placement raising $1.5m before costs under a
strongly supported two-tranche placement:
Tranche 1 raised $1.13m
o Tranche 2 will raise $369k and is subject to shareholder
approval at a General Meeting to be held on 12 August 2026.
criticalmineralsgroup.com.au
• CEO, Scott Winter attended the EXIM and Select USA conferences in Washington DC,
USA during April and May and continued discussions with government agencies on
funding and development opportunities;
• The IPCM Federal Grant is currently suspended, delays in the QRCUF shared
processing facility have affected certain grant milestones. CMG is moving forward
with alternative options and discussions are ongoing with the Department.
Critical Minerals Group Limited (ASX:CMG), (Critical Minerals Group, CMG, or the Company)
is pleased to provide shareholders with the following update in relation to the Company’s
activities for the quarter ended 30 June 2026 (Quarter).
COMPANY ACTIVITIES
Upstream, midstream – Pre-Feasibility Study Lindfield Vanadium Project and Vanadium
Electrolyte facility
CMG has completed a Pre-Feasibility Study (PFS) for the Lindfield Vanadium Project, an
integrated development comprising an open-cut vanadium mine near Julia Creek, north-
west Queensland, and a Vanadium Electrolyte (VE) manufacturing facility at the Parkes
Special Activation Precinct, NSW. The PFS supports progression to a Definitive Feasibility Study
(DFS) and, subject to funding, approvals, offtake and completion of further technical work, a
Final Investment Decision (FID) targeted for calendar year 2027.1
PFS Highlights (3 Mtpa Preferred Case)
Pre-Tax NPV A$821M Pre-Tax IRR 26.6%
Post-Tax NPV A$458M Post-Tax IRR 18%
Total Capital Cost A$981M Payback Period 7 years
Mine Life 31 years Annual ROM Feed 3 Mtpa
Peak Funding
Requirement
A$736M
Avg. Annual V₂O₅
Production
10,577 t
(Yr 1–16)
1
The PFS results, production target and forecast financial information referred to in this report should be read
together with the Company’s prior ASX announcement released 21 July 2026, containing the applicable JORC Code,
production target and forecast financial information disclosures. The Company confirms that it is not aware of any
new information or data that materially affects that previously announced information and that all material
assumptions and technical parameters underpinning that information continue to apply and have not materially
changed.
criticalmineralsgroup.com.au
Study prepared to ±25% accuracy (March 2026 A$); 9% discount rate; AUD/USD 0.67. The 3
Mtpa scenario is the preferred development pathway under the PFS and remains subject to
completion of the DFS, permitting, funding, offtake arrangements and other customary
project development risks.
Key strategic takeaways
• Staged development: VE facility to be commissioned ahead of the Lindfield mine using
third-party V₂O₅ feedstock, bringing forward first revenue to 2028 and reducing peak
funding exposure.
• Mineral Resource Estimate of 713 Mt at 0.32% V₂O₅ (491 Mt Indicated, 222 Mt Inferred); no Ore
Reserve has been declared at this stage pending further drilling under the DFS. The Mineral
Resource Estimate should be cross-referenced to the Company’s original ASX
announcement and accompanied by the usual confirmation that the Company is not
aware of any new information or data that materially affects the Mineral Resource
information and that all material assumptions and technical parameters continue to apply
and have not materially changed.
• Three Board-endorsed priority workstreams for the DFS:
1) metallurgical pilot plant programme to confirm/improve vanadium recovery – the
single highest value lever;
2) securing long-term, competitively priced sulphuric acid and sodium hydroxide
supply; and
3) advancing government concessional finance and binding offtake negotiations.
• Market opportunity: the Company is assessing demand for vanadium flow battery
applications, including grid firming and data-centre related load growth.
• Funding not yet secured; the Company is pursuing equity markets, debt, and concessional
government facilities (NAIF, NRF, EFA, Critical Minerals Facility).
Key Risks and Mitigants
Risk Area Description Key Mitigant
Product
Quality
Consistently achieving ≥99.5% V₂O₅
purity
Pilot plant programme; closed-
loop impurity study in DFS
Reagent Costs
High acid consumption drives OPEX
above incentive levels
Beneficiation optimisation; on-
site acid plant (3–4 Mtpa)
criticalmineralsgroup.com.au
Funding
Raising sufficient capital from DFS
to FID/construction
Early government funding
engagement; VE facility lowers
capital entry point
Offtake &
Revenue
Delays securing binding offtake /
pricing
Advance product qualification;
early VFB developer
engagement
Permitting
EIS delays or conditions postponing
FID
Early regulator engagement;
Coordinated Project application
Exchange Rate
AUD/USD volatility affects revenue
vs. costs
FX sensitivity modelled; natural
AUD hedge; offtake floor pricing
Resources &
Reserves
~20% of Mineralised Material
overlain by constrained land
Working through resolution with
DNRMMRRD
Metallurgical Test Work
No additional testwork was conducted in the Quarter with the focus on finalising the PFS
report and commencement of planning for the DFS. A full audit of material stored at
Brisbane Metlabs was undertaken to facilitate the planning process, including material
requirements from the upcoming drill program at Lindfield.
CMG is participating in a Trailblazer Project titled “Optimising Vanadium Extraction and
Processing from the Toolebuc Formation through Advanced Characterisation” with James
Cook University (JCU) and has supplied drillcore from the previous drill programs in 2022 and
2023 for detailed mineralogical analysis. Work on this project has commenced and the first
formal update of project outcomes will be presented at the JCU Research Showcase on 12
August 2026.
Development, Environmental Studies and Approvals/Permits
No additional activities were conducted on the Lindfield environmental studies required for
approvals in the Quarter. Relevant environmental study information collected to date was
evaluated and included in the PFS report.
criticalmineralsgroup.com.au
PROJECTS AND EXPLORATION UPDATE
During the Quarter, CMG applied to consolidate the existing vanadium tenements into a
single Project titled “The Lindfield Project”. CMG also submitted a tender for the ground
immediately to the west of EPM27872 Lindfield in a competitive tender process. Outcomes will
not be known until later in the year.
The below map displays the locations of CMG’s current vanadium tenements.
Image: Location of CMG Limited Vanadium tenements in the Julia Creek area
Lindfield Project (EPM 27872)
The Lindfield Project is CMG’s flagship project, located 30km east of Julia Creek in North-West
Queensland. The Lindfield Project consists of 92 sub-blocks, covering 295km2
. An update on
this project is outlined below:
Progression of Pilot Plant Test Work
No additional bench or pilot scale work was conducted during the Quarter, with activities
focused on completion of the PFS report. Planning for the next phase of work has
commenced.
Specific Environmental (EIS) Studies Conducted to Advance Approvals
Please see update above.
Upcoming Works Program
The activities over the next 6 months will focus primarily on the work to plan and execute on
the Feasibility Study. The activities include:
criticalmineralsgroup.com.au
• Planning for the commencement of activities associated with the Definitive Feasibility
Study.
o Geology: Plan and confirm timing of upcoming drill program and engage
relevant stakeholders,
o Metallurgy: Complete detailed planning of additional metallurgical testing plan
for both bench scale and pilot scale testing required for FS and detailed design,
o Engineering Planning: Assess and engage supporting design and engineering
firms to support the FS (Mining, NPI, power, water),
o Approvals planning: complete a gap analysis of EIS-focused work undertaken
to date and complete detailed planning of additional works required in
anticipation of receipt of the actual terms of reference,
o Procurement: engagement with suppliers of major reagents and supply items,
• Continue dialogue with relevant stakeholders on progress of the Lindfield Project with a
particular focus on landholders, McKinlay Shire Council and local businesses.
• Continue to support the Trailblazer Project “Optimising Vanadium Extraction and
Processing from the Toolebuc Formation through Advanced Characterisation” being
run through JCU in Townsville.
• Continue to engage with DETSI and DNRMMRRD regarding approvals next steps
• Engagement and negotiation of Offtake agreements for supply of vanadium
electrolyte.
• Engagement with domestic and international ECA’s, and government agencies
regarding funding for critical minerals in support of Lindfield and vanadium electrolyte
facility development.
Lara Downs Project (EPM 28635) and Lindfield North Project (EPM 28636)
The Lara Downs and Lindfield North Project are both located within 70km (north) of Julia
Creek, with the Lindfield North Project adjoining the existing Lindfield Project and the Lara
Downs Project within 35km of the Lindfield Project. Both of these tenements are included in
the consolidated project application.
Lindfield North consists of 36 sub-blocks covering 115 km2
. Lara Downs consists of 118 sub-
blocks covering 378km2
.
Exploration Plan for Lindfield North and Lara Downs Projects
CMG is of the opinion that both the Lindfield North Project and the Lara Downs Project can
benefit from the learnings of, and results from, exploration in the region to date.
criticalmineralsgroup.com.au
There is no further update for these tenements for this Quarter.
Upcoming Works Program
There is no work currently scheduled for these two tenements in the upcoming September
Quarter.
Whinmoor Project (EPM 28631)
The Whinmoor Project consists of 100 sub-blocks covering 320 km² and is located 60km north
of Julia Creek. This tenement is included in the consolidated project application. The
Whinmoor Project intends to extend on exploration by previous explorers and known
extensions to vanadium mineralisation in the Company’s Lindfield Project.
There is no further update for this tenement for the Quarter.
Upcoming Works Program
There is no work scheduled for this tenement in the September 2026 quarter.
Figtree Creek Project (EPM 27998) and Lorena Surrounds Project (EPM 27999)
No substantive exploration activities or fieldwork were undertaken on the Tenements during
the Quarter. The Company will continue to assess commercial options.
criticalmineralsgroup.com.au
ASX ANNOUNCEMENTS DURING THE QUARTER
This quarterly report contains information released to ASX, which has been reported in
accordance with the JORC Code (where required). These announcements can be found on
the Company’s website at: https://investors.criticalmineralsgroup.com.au/announcements
• 23 April 2026 Launch of Investor Hub
• 30 April 2026 Quarterly Activities/ Appendix 5B Cash Flow Report
• 11 May 2026 Notice of General Meeting/ Proxy Form
• 10 June 2026 Results of Meeting
• 15 June 2026 Investor Presentation
• 18 June 2026 Trading Halt
• 22 June 2026 $1.5M Placement to Advance Vanadium Electrolyte Strategy
• 22 June 2026 Proposed issue of securities - CMG
• 24 June 2026 Details of Auditor appointment / Resignation
• 29 June 2026 Application for quotation of securities – CMG
• 29 June 2026 Cleansing notice
FINANCIAL COMMENTARY
The Quarterly Cashflow Report (Appendix 5B) for the Quarter provides an overview of the
Company’s financial activities.
Exploration expenditure for the Quarter was $521,921, while corporate and other expenditures
totalled $542,810 (including $409,607 in salaries and director fees).
In accordance with the Company’s disclosure obligations under ASX Listing Rule 5.3.5, the total
amount paid to directors and their associates during the Quarter (item 6.1 of the Appendix 5B)
was $148,750 and includes the Managing Director’s remuneration.
criticalmineralsgroup.com.au
Forward-Looking Statements
This announcement may include forward-looking statements. Forward-looking statements
include, but are not limited to, statements concerning exploration and development
activities, feasibility studies, Mineral Resource and production target assumptions, forecast
financial information, funding, permitting, offtake, project development timelines, capital and
operating costs, commodity pricing, exchange rates, market demand and future revenue.
When used in this document, words such as “could”, “plan”, “estimate”, “expect”, “intend”,
“may”, “potential”, “should”, “target”, “forecast” and similar expressions are forward-looking
statements. Although the Company believes that it has reasonable grounds for the forward-
looking statements at the date of this announcement, such statements are subject to known
and unknown risks, uncertainties and assumptions, and actual results may differ materially
from those expressed or implied. No assurance can be given that the Company will achieve
its stated objectives, development timetable, funding outcomes, production targets or
forecast financial information.
This announcement was approved by the board of directors of CMG.
For more information contact:
Scott Winter
CEO and Managing Director
info@criticalmineralsgroup.com.au
(07) 3132 3504
criticalmineralsgroup.com.au
Schedule 1 – Tenement Schedule as of 30 June 2026
Project
Name
Location Tenement Status
Equity at 31
March 2026
Equity at 30
June 2026
Changes
during
Quarter
Lindfield
Project
Julia Creek EPM 27872 Granted 100% 100% -
Figtree
Creek
Project
Cloncurry EPM 27998 Granted 100% 100% -
Lorena
Surrounds
Project
Cloncurry EPM 27999 Granted 100% 100% -
Whinmoor
Project
Julia Creek EPM 28631 Granted 100% 100% -
Lara Downs
Project
Julia Creek EPM 28635 Granted 100% 100% -
Lindfield
North
Project
Julia Creek EPM 28636 Granted 100% 100% -
Rule 5.5
ABN
Current quarter
Year to date
(12 months)
$A’000 $A’000
1 Cash flows from operating activities
1.1 Receipts from customers
1.2 Payments for
(a) exploration and evaluation - - 3
(b) development
(c) production
(d) staff costs - 410 - 1,578
(e) administration and corporate costs - 133 - 1,687
1.3 Dividends received (see note 3)
1.4 Interest received 1 18
1.5 Interest and other costs of finance paid
1.6 Income taxes paid
1.7 Government grants and tax incentives - 900
1.8 Other (provide details if material) 3 12
Current quarter
Year to date
(12 months)
$A’000 $A’000
2 Cash flows related to investing activities or for:
2.1 Payment to acquire
(a) entities
(b) tenements
(c) property plant and equipment - 30
(d) exploration & evaluation - 522 - 1,193
(e) investments
(f) other non-current assets - 200
Quarter ended (“current quarter”)
91 652 994 726 Jun-26
Appendix 5B
Name of entity
Critical Minerals Group Limited
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Consolidated statement of cash flows
1.9 Net cash from/(used in ) operating activities - 539 - 2,338
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas explortion entity quarterly cashflow report
Current quarter
Year to date
(12 months)
$A’000 $A’000
2.2 Proceeds from disposal of:
(a) entities
(b) tenements
(c) property plant and equipment
(d) investments
(e) other non-current assets
2.3 Cashflows from loans to other entities
2.4 Dividends received
2.5 Other (provide details if material)
Net cash from/(used in) investing activities - 522 - 1,023
3 Cash flows related to financing activities
3.1
Proceeds from issues of of equity securities
(excluding convertible debt secutities)
1,131 3,146
3.2 Proceeds from issues of convertible debt securities
3.3 Proceeds from exercise of options
3.4
Transaction costs related to issues of equity securities or convertible
debt securities
- 97 - 222
3.5 Proceeds from borrowings
3.6 Repayment of borrowings
3.7 Transaction costs related to loans and borrowings
3.8 Dividends paid
3.9 Other (provide details if material)
3.10 Net cash from/(used in) financing activities 1,034 2,924
4
Net increase (decrease) in cash and cash equivalents for the period
4.1 Cash and cash equivalents at beginning of period 850.0 1,260.0
4.2 Net cash from/(used in) operating activities (Item 1.9 above) - 538.5 - 2,337.5
4.3 Net cash from/(used in) investing activities (Item 2.6 above) - 522.0 - 1,023.0
4.4 Net cash from/(used in) financing activities (Item 3.10 above) 1,034.0 2,924.0
Current quarter
Year to date
(12 months)
$A’000 $A’000
4.5 Effect of movement in exchange rate on cash held
4.6 Cash and cash equivalents at end of the quarter 823 823
Consolidated statement of cash flows
2.6
Consolidated statement of cash flows
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas explortion entity quarterly cashflow report
5 Reconciliation of cash and cash equivalents Current quarter
Previous quarter
at the end of the quarter (as shown in the consolidated statement of cash
flows) to the related items in the accounts
$A’000 $A’000
5.1 Bank balances 823 849
5.2 Call deposits
5.3 Bank overdrafts
5.4 Other (provide details)
5.5
Cash and cash equivalents at end of quarter (should equal item 4.6
above)
823 849
6 Current quarter
$A'000
6.1
Aggregate amount of payments to related parties and their
associated included in item 1.2
149
6.2
Aggregate amount of payments to related parties and their
associates included in item 2.3
6.3
Aggregate amount of payments to related parties and their
associates included in item 3.4
7 Financing facilities
NOTE: The term "facility" included all forms of financing arrangements
avaliable to the entity
Add notes as necessary for an understanng of the sources of finance avaliable
to the entity.
Total facility amount
at quarter end
Amount drawn at
quarter end
$A’000 $A’000
7.1 Loan facilities
7.4 Total financing facilities
7.5 Unused financing facilites available at the quarter end
7.6
Include below a description of each facility above, including the lender, interest rate, maturity
date and whether it is secured or unsecured. If any additional facilities have been entered
into or are proposed to be entered into after quarter end, include details of those facilities as
well.
Note: if any amounts are shown in 6.1, 6.2 or 6.3 your quarterly report must a description and an
explanation for, such payments
Payments of salary to CEO/ Managing Director and Director Fees.
7.3
Payments to related parties of the entity and their associates
Other (please specify)
7.2 Credit standby arrangements
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas explortion entity quarterly cashflow report
8
Estimated cash available for future operating
activities
$A'000
8.1 Net cash from / (used in ) operating activities (Item 1.9) - 539
8.2
Payment s for exploration & evaluation classified as investing
activities) (item 2.1(d))
- 522
8.3 Total relevant outgoings (Item 8.1 + Item 8.2) - 1,061
8.4 Cash and equivelants at quarter end (item 4.6) 823
8.5 Unused finance facilites avaliable at quarter end (item 7.5) -
8.6 Total available funds (Item 8.4 + Item 8.5) 823
8.7
Estimated quarters of funding available (Item 8.6 divided by Item
8.3)
0.8
8.8
8.8.1 Does the entity expect that it will continue to have the current level of net operating cash flow for the
time being and if not why not ?
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further cash to fund its
operation and , if so, what are those steps and how likely does it believe that they will be successful?
8.8.3 Does the entity expect to be able to continue its operations and to meet its business objectives and , if so ,
on what basis?
Note: if the entity has reported positive net operating cashflows in item 8.3 answer item 8.7 as "N/A. Otherwise, a
figure for the estimated quarters of funding available must be included in item 8.7
If Item 8.7 is less than 2 quarters, please provide answers to the following questions:
Answer:
Yes. The Company's expenditure will continue to track its near term objectives that include the development of the
Lindfield Project and the establishment of the vanadium electrolyte business and manufacturing facility and
pursuing opportunities for Vanadium Flow Battery installations.
Answer:
Yes. The Company has been able to raise capital as required to fund its business as most recently demonstrated
with the sucessful Placement in June 2026. The Company will continue to explore funding options to support the
Company's requirements.
Yes. Based on its history of successful capital raising and the ongoing support of major shareholders, and potential
investors and the continuted execution of its dvelopment objectives.
Note: where item 8.7 is less than 2 quarters, all questions 8.8.1, 8.8.2 and 8.8.3 above must be answered
Answer:
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas explortion entity quarterly cashflow report
1
2
Date: 31-Jul-26
Authorised by: The Board
Notes
1
2
3
4
5
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”. If it has
been authorised for release to the market by a committee of your board of directors, you can insert here: “By the [name of board
committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a disclosure committee, you
can insert here: “By the Disclosure Committee”.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards and gives
a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a sound system of risk
management and internal control which is operating effectively.
This statement does give a true and fair view of the matters disclosed.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s
activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes
to disclose additional information over and above the minimum required under the Listing Rules is encouraged to do so.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and
provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to
this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX
pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity
This statement has been prepared in accordance with accounting standards and policies which comply
with Listing Rule 19.11A.
Compliance statement