Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 1
ASX Announcement
ASX: CMG
30 October 2026
QUARTERLY ACTIVITIES REPORT AND APPENDIX 5B
For the quarter ended 30 September 2026
713 Mt
Lindfield MRE at 0.32% V₂O₅
100%
PFS mine plan area now
within EPM 27872
55 holes
First DFS drilling program
and first at Lindfield since
2023, approx. 1,320 metres
Up to $2.05M
Placement and SPP
announced 19 October 2026
KEY HIGHLIGHTS
• CMG released its Pre-Feasibility Study (PFS) for the integrated Lindfield Vanadium Project on 20
July 2026, with supplementary information on 21 July 2026. The 3 Mtpa preferred case returned
a pre-tax net present value (NPV) of $821 million and a pre-tax internal rate of return (IRR) of
26.6%, supporting progression to a Definitive Feasibility Study (DFS)1
.
• During the Quarter management undertook detailed planning of the DFS, which is structured so
that the drilling, metallurgical, approvals and engineering workstreams run in parallel.
• Site works for the first DFS field program, a drilling program of approximately 55 core holes for
approximately 1,320 metres, commenced in October 2026, as announced on 20 October 2026,
and drilling commenced on 27 October 2026. It is the first drilling at Lindfield since 2023.
• Mr Pat Kelly, previously Chief Operating Officer, was appointed Interim Chief Executive Officer
effective 1 September 2026 following the resignation of Mr Scott Winter as Managing Director
and Chief Executive Officer.
• Tranche 2 of the June 2026 placement, 5,093,006 shares at $0.0725 raising approximately $0.37
million, was approved by shareholders at the General Meeting held on 12 August 2026 and
issued on 1 September 2026.
• On 19 October 2026 the Company announced that the Queensland Department of Natural
Resources and Mines, Manufacturing and Regional and Rural Development (the Department)
had approved the addition of previously excluded land to Exploration Permit for Minerals (EPM)
27872, bringing all mineralised material in the PFS mine plan within the Company’s permit and
resolving a risk rated HIGH in the PFS.
• On 19 October 2026 the Company announced a placement and Share Purchase Plan (SPP) to
raise up to approximately $2.05 million (before costs), the proceeds of which are intended to
fund the commencement of DFS workstreams. The placement was led by existing shareholders,
and Mr Gerhard Redelinghuys was appointed as a Non-Executive Director.
1The PFS results, production target and forecast financial information in this report should be read with the Company’s ASX announcements
of 20 and 21 July 2026, which contain the applicable JORC Code and forecast financial information disclosures.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 2
Critical Minerals Group Limited (ASX: CMG) (Critical Minerals Group, CMG or the Company) is pleased
to provide shareholders with the following update in relation to the Company’s activities for the quarter
ended 30 September 2026 (Quarter).
COMPANY ACTIVITIES
Lindfield Vanadium Project Pre-Feasibility Study
On 20 July 2026 CMG released the PFS for the Lindfield Vanadium Project (Lindfield or the Project), an
integrated development comprising an open-cut vanadium mine near Julia Creek in north-western
Queensland and a Vanadium Electrolyte (VE) manufacturing facility at the Parkes Special Activation
Precinct in central New South Wales. Supplementary information on capital and operating costs and
the Mineral Resource breakdown by horizon was released on 21 July 2026.
The PFS evaluated three production scenarios of 1 Mtpa, 3 Mtpa and 4 Mtpa of run of mine (ROM)
economically mineable mineralised material and identified the 3 Mtpa case as the preferred
development pathway. The PFS supports progression to a DFS.
Table 1 PFS highlights, 3 Mtpa preferred case
Pre-tax NPV $821M Pre-tax IRR 26.6%
Post-tax NPV $458M Post-tax IRR 18%
Initial capital cost $981M Payback period 7 years
Mine life 31 years Annual ROM feed 3 Mtpa
Peak funding requirement $736M Average annual V₂O₅ (Years 1 to 16) 10,577 t
Study prepared to an accuracy of ±25% (March 2026 $), using a 9% discount rate and an AUD/USD exchange rate of 0.67. The 3
Mtpa scenario remains subject to completion of the DFS, permitting, funding, offtake arrangements and other customary project
development risks.
The PFS adopts a staged development, with the VE facility commissioned ahead of the Lindfield mine
using third-party sourced vanadium pentoxide (V₂O₅) feedstock, to bring forward first revenue and
reduce peak funding exposure. The timing and location of the VE facility will be reassessed in the DFS.
Sensitivity analysis showed Project returns are most exposed to VE price, grade of the mineralised
material and metallurgical recovery.
The PFS identified three priority workstreams for the DFS:
• the metallurgical pilot plant program to optimise vanadium recovery, the single highest value lever
for the Project;
• securing long-term, competitively priced supply of sulphuric acid and sodium hydroxide, which
together represent a significant proportion of processing operating costs; and
• advancing concessional finance and binding offtake negotiations.
Definitive Feasibility Study
Following release of the PFS, the Company’s activities during the Quarter focused on planning the DFS
and preparing for its first field program. The Company is advancing three interlinked workstreams: the
DFS, where the critical path is the process engineering that depends on drill core from the drilling
program; the environmental approvals, where the critical path is the field studies; and the Mining Lease
application, which involves stakeholder negotiations. Each workstream is being advanced within the
funding available.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 3
DFS planning
The planning built on the plan prepared at the conclusion of the PFS and defined the scope, sequencing,
cost and resourcing of each workstream against the PFS findings, in particular the priority the PFS
placed on the metallurgical pilot plant program. The DFS program, budget and timetable are being
finalised, and the Company is pursuing equity, debt and concessional government finance.
The initial workstreams comprise the drilling program, bench-scale metallurgical test work, a
groundwater baseline study and lodgement of the Coordinated Project application and EPBC Act
referral. Site works commenced in October 2026 and drilling commenced on 27 October 2026. The later
workstreams, including the metallurgical pilot plant campaign, the water investigation program, the EIS
and engineering, will follow the drilling program and will proceed as funding is secured.
Geology and resource drilling
The DFS drilling program was designed following completion of the PFS to address a number of the
geological, metallurgical, geotechnical, groundwater and mine planning matters the PFS identified for
resolution in the DFS. Stage 1 of the program comprises approximately 55 vertical holes for
approximately 1,320 metres, with up to three holes completed as groundwater monitoring bores,
together with eight shallow geotechnical auger holes. Planning during the Quarter included the drilling
contract, geological supervision and assay arrangements and agreement with the landholder on the
drill pad and access track locations and the compensation payable under the Company’s existing
conduct and compensation agreement for Lindfield Station.
The program is the first of two stages of resource drilling planned for the DFS. It is designed to increase
geological confidence on the northern, southern and eastern perimeters of the PFS mine development
area, where drill hole spacing in the weathered Indicated Resources is typically 1,000 metres, and to
support an updated Mineral Resource Estimate (MRE). A second stage of closer-spaced drilling is
planned for the 2027 dry season with the objective of upgrading the initial proposed mining zone to a
Measured Mineral Resource and supporting a maiden Ore Reserve for the DFS. There is no certainty that
further drilling will result in the upgrade of any part of the MRE to a higher confidence category or in the
declaration of an Ore Reserve.
J&S Drilling was engaged as drilling contractor, and geological supervision is being provided by
Measured Group, whose Principal Geologist, Mr Adrian Buck, is the Competent Person for the Lindfield
MRE. This provides continuity from the existing MRE through to the updated MRE that will follow the
program. Site works commenced in October 2026, as announced on 20 October 2026. The drilling
contractor mobilised to site on 26 October 2026 and drilling commenced on 27 October 2026.
Metallurgy
Selected drill sites will be twinned to provide approximately 3 tonnes of core material. This will be
composited by mineralised horizon to provide feed for the pilot plant campaign. Remaining drill core
selected from previous drilling programs, along with selected holes from the 2026 program will be
composited to provide samples for bench-scale variability test work at Brisbane Metlabs, which has
undertaken the majority of the Company’s metallurgical test work to date.
The bench-scale variability program will measure beneficiation performance, leach response,
purification and final product generation, along with reagent consumption for each horizon for the
nominal first years of mining operation. This will include assessing acid consumption, which is a
significant component of processing operating costs.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 4
A limited amount of test work was conducted during the Quarter to evaluate a potential alternative
oxidant in the leach. The initial results were encouraging, and additional tests are currently being
planned to fully evaluate the effects with recycling streams included.
CMG is participating in a Trailblazer Project titled “Optimising Vanadium Extraction and Processing from
the Toolebuc Formation through Advanced Characterisation” with James Cook University (JCU) and
testing of the drill core samples supplied by CMG is due to commence in early November 2026.
Approvals and the Office of the Coordinator-General
The Company’s Preliminary Approvals Strategy for the Project was developed in consultation with the
Office of the Coordinator-General (OCG) and the Queensland Critical Minerals Office, reflecting the role
of the OCG in coordinating the planning and cumulative assessment of critical minerals developments
in the Northwest Minerals Province. As reported in the PFS, the Company has prepared an Initial Advice
Statement (IAS) supporting an application for the Project to be declared a Coordinated Project under
the State Development and Public Works Organisation Act 1971 (Qld), and a referral under the
Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act).
During the Quarter the Company continued its engagement with the OCG on the approvals pathway
for the Project and received a proposal from its Queensland-based environmental consultant to update
the IAS, prepare the Coordinated Project application to the Coordinator-General and the referral to the
Commonwealth under the EPBC Act and conduct pre-lodgement meetings with the state and federal
regulators. Lodgement of the application and the referral had been held for 12 months pending
resolution of the excluded land within EPM 27872 (see Lindfield Project below). The Department’s
approval of the addition of the excluded land to EPM 27872 was announced on 19 October 2026.
Lodgement of both documents is targeted before the end of calendar year 2026. A Coordinated Project
declaration and the Terms of Reference for the EIS that follow it will set the scope of the EIS specialist
studies in the DFS.
With the full PFS mine plan area now held within EPM 27872 (see Lindfield Project below), the Company
is planning to recommence its project approvals work, including the Mining Lease application and the
EIS field assessments. Stakeholder liaison and negotiations for the Mining Lease application will
commence as part of this work.
During the Quarter, the Interim Chief Executive Officer visited Julia Creek to meet with McKinlay Shire
Council and landholders of EPM 27872 and the Company’s other vanadium tenements. The Interim Chief
Executive Officer also met with Richmond and Cloncurry Shire Council personnel to discuss
expectations and potential business opportunities. The Company has begun discussions with relevant
stakeholders on rehabilitation options, ongoing land management and mine closure planning to inform
the EIS.
Water
Water supply for the Project is being progressed on two fronts, site baseline data for the EIS and long-
term project water supply. Three water bores at Lindfield have been subject to monitoring over the past
two years and the three new groundwater monitoring bores in the DFS drilling program will add baseline
groundwater level and quality data ahead of the environmental impact assessment.
For process water, the Coordinator-General’s Stage 1 Strategic Assessment of water delivery options for
the Julia Creek and Richmond Critical Minerals Zone (February 2025) is assessing shared water supply
options for the zone, combining Great Artesian Basin bore water and surface water harvesting. During
the Quarter the Company progressed the DFS water supply strategy, which contemplates investigation
bores into the Hooray Sandstone aquifer with pump testing and monitoring of other regional water
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 5
bores, followed by groundwater modelling and the water licence application. A groundwater baseline
study is being commissioned from an independent hydrogeologist with a report due by the end of
December 2026. The study will consolidate the existing publicly available groundwater bore data and
the regional assessment and will set the scope of the investigation program.
Engineering
The eight geotechnical auger holes in the DFS drilling program will provide the first site-specific soil
strength and foundation data required for engineering design of infrastructure foundations, pit wall,
waste dump and dam slope design parameters. Engineering design work, including the engagement
of design and engineering firms for mining, non-process infrastructure, power and water, will follow the
drilling and metallurgical programs. The Chief Technology Officer has issued expressions of interest to
engineering firms for the supervision of the pilot plant campaign and the process engineering for the
DFS. The Company has also designed the decision trees that will direct the metallurgical analysis.
Responses, and a refreshed scope and quotation for the laboratory and engineering work, are expected
by the end of December 2026 and will inform the DFS budget.
CORPORATE
Leadership transition
On 28 August 2026 the Company announced that Mr Scott Winter had resigned as Managing Director
and Chief Executive Officer with effect from 1 September 2026. Mr Pat Kelly, who joined CMG as Chief
Operating Officer in November 2024, was appointed Interim Chief Executive Officer effective 1
September 2026. Mr Kelly retains responsibility for the Company’s operations. The Company’s strategy
and work program are unchanged. As noted in the Company’s announcement of 28 August, the Board
thanks Mr Winter for his contribution to the Company.
Placement and General Meeting
At the General Meeting held on 12 August 2026 shareholders ratified the issue of the 15,596,652 Tranche
1 Placement Shares and approved the issue of the 5,093,006 Tranche 2 Placement Shares at $0.0725
per share. The Tranche 2 Placement Shares were issued on 1 September 2026, raising approximately
$0.37 million (before costs) and completing the $1.5 million placement announced on 22 June 2026.
Cost reduction
During the Quarter the Board reviewed the Company’s corporate overhead and the organisational
structure needed to deliver the DFS. Decisions arising from the review have reduced corporate overhead
and, amongst other initiatives, the full-time Chief Financial Officer role has been made redundant, as
announced on 19 October 2026. Ms Trudy Walsh has resigned as Joint Company Secretary and will
continue in the role until the end of her notice period in mid-January 2027 to ensure an orderly transition
to a new finance support arrangement. The Board thanks Ms Walsh for her contribution to the Company.
Mr Adam Gallagher continues as Company Secretary. The departures of the former Managing Director
and the Chief Financial Officer, together with the Interim Chief Executive Officer also carrying the Chief
Operating Officer role, reduce the Company’s annualised fixed executive remuneration by
approximately $0.8 million.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 6
October 2026 placement and Share Purchase Plan
On 19 October 2026 the Company announced a placement and SPP to raise up to approximately $2.05
million (before costs), led by existing shareholders including cornerstone shareholder Idemitsu Lindfield
Pty Ltd (Idemitsu) and substantial shareholder Mr Gerhard Redelinghuys. The unconditional component
of 9,341,214 shares at $0.06 was issued on 20 October 2026, raising $0.56 million. The subscriptions by
Idemitsu and Mr Redelinghuys are subject to shareholder approval at the AGM. Following that approval
Idemitsu would hold between approximately 32.9% and 33.9%, and Mr Redelinghuys and his related
entities between approximately 12.6% and 14.2%, depending on SPP take-up. The SPP closes at 5.00pm
(Sydney time) on 4 November 2026. Full details are set out in the announcement of 19 October 2026
and the SPP offer booklet released on 21 October 2026.
The Annual General Meeting (AGM) will be held on Monday, 30 November 2026, at which the Company
intends to seek approval for the conditional components of the placement.
Board and substantial holders
Mr Gerhard Redelinghuys was appointed as a Non-Executive Director effective 19 October 2026 and will
stand for election at the AGM. Following the issue of the unconditional component of the October 2026
placement, Latimore Family Pty Ltd as trustee for The Latimore Family Trust, an entity associated with
Mr Matt Latimore, became a substantial holder of the Company on 20 October 2026 with a relevant
interest in 10,389,497 shares, representing a voting power of 7.7%. Mr Latimore is the founder and
President of M Resources, a Queensland-based coal marketing and investment group, and a Non-
Executive Director of Stanmore Resources Limited (ASX: SMR). The Board welcomes Mr Latimore’s
increased investment in the Company.
Commonwealth grant
As reported in the June 2026 quarterly report, the Company’s grant under the Commonwealth
International Partnerships in Critical Minerals program was suspended. Following completion of the
required reporting and independent audit, the Company and the Department of Industry, Science and
Resources have agreed to terminate the grant agreement by mutual consent, with no repayment of
the grant funds received. The deed of termination is in the course of execution.
PROJECTS AND EXPLORATION UPDATE
The Company holds six granted EPMs in north-western Queensland (Schedule 1). During the Quarter the
Company’s application to consolidate its vanadium tenements into a single project under the Mineral
Resources Act, the Lindfield Project, was approved, which will simplify tenement management. The
below map displays the locations of CMG’s current vanadium tenements.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 7
Figure 1 Location of CMG Limited vanadium tenements in the Julia Creek area
Lindfield Project (EPM 27872)
The Lindfield Project is CMG’s flagship project, located approximately 30 km east of Julia Creek in north-
western Queensland. EPM 27872 comprises 92 sub-blocks covering approximately 295 km².
The north-western portion of EPM 27872 was subject to a historical overlap with MDL 522, which divided
four Lindfield sub-blocks in half, with the affected half of each sub-block excluded from the permit when
it was granted in December 2021. The PFS identified the exclusion as a HIGH rated Resources and
Reserves risk affecting up to approximately 20% of the mineralised material in the PFS mine plan. The
Company continued its engagement with the Department on this matter during the Quarter.
An application to renew EPM 27872 was lodged in September 2026. Following a review of all of the
Company’s vanadium tenements, the Board decided to renew EPM 27872 in its current form of 92 sub-
blocks and to surrender 46 sub-blocks from EPM 28635 (Lara Downs) as the offset required under the
Mineral Resources Act. The sub-block offset has been approved. During the Quarter the Company’s
application to consolidate its vanadium tenements into a single project under the Mineral Resources
Act, the Lindfield Project, was also approved, which will simplify tenement management.
On 19 October 2026 the Company announced that the Department had approved, under section 176A
of the Mineral Resources Act 1989 (Qld), the addition of the previously excluded land to EPM 27872. All
mineralised material in the PFS mine plan is now held within the Company’s permit. The MRE of 713 Mt
at 0.32% V₂O₅ stands as reported and the PFS mine plan is unaffected. The added area is included in
the DFS drilling program. Figure 2 shows the indicative general arrangement of the Project within EPM
27872, including the first draft Mining Lease application area, the indicative open-cut and processing
infrastructure footprints and the area formerly restricted by MDL 522 that has now been added to the
permit.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 8
Figure 2 Lindfield Project indicative general arrangement
Source: Lindfield Vanadium Project Pre-Feasibility Study, May 2026 (Figure 2-11).
Lara Downs Project (EPM 28635) and Lindfield North Project (EPM 28636)
The Lara Downs and Lindfield North tenements are both located within 70 km north of Julia Creek.
Lindfield North adjoins the Lindfield Project and Lara Downs lies within 35 km of it. Both of these
tenements are included in the consolidated project approval.
Lindfield North consists of 36 sub-blocks covering 115 km2
. After the surrender of 46 sub-blocks to offset
the Lindfield EPM 27872 renewal application, Lara Downs will consist of 72 sub-blocks covering 230 km2
.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 9
No field activities were undertaken on these tenements during the Quarter and none are scheduled for
the December 2026 quarter.
Whinmoor Project (EPM 28631)
The Whinmoor Project comprises 100 sub-blocks covering approximately 320 km² and is located 60 km
north of Julia Creek. It is intended to extend exploration by previous explorers and known extensions of
the vanadium mineralisation in the Lindfield Project. No field activities were undertaken during the
Quarter and none are scheduled for the December 2026 quarter.
Figtree Creek Project (EPM 27998) and Lorena Surrounds Project (EPM 27999)
No substantive exploration activities or fieldwork were undertaken on these tenements during the
Quarter. The Company continues to assess commercial options.
UPCOMING WORKS PROGRAM
Activities over the next three to four months will focus on the first DFS workstreams, including:
• completion of the DFS drilling program ahead of the wet season, with assay results expected from
late 2026;
• continuation of bench-scale test work at Brisbane Metlabs and planning of the metallurgical pilot
plant campaign;
• planning of the second stage of DFS resource drilling for the 2027 dry season;
• completion of the conditional components of the October 2026 placement following the AGM on 30
November 2026,;
• recommencement of project approvals, including the EIS, Mining Lease application and EPBC Act
referral, with meetings with the relevant government departments to confirm approval
requirements ahead of the Terms of Reference, together with stakeholder liaison with landholders,
McKinlay Shire Council and local businesses;
• lodgement of the Coordinated Project application and the EPBC Act referral, targeted before the
end of calendar year 2026, and completion of the groundwater baseline study to set the scope of
the DFS water investigation program;
• engagement of design and engineering support for the DFS and continued engagement with
suppliers of major reagents;
• continued engagement with prospective vanadium electrolyte customers and with providers of
concessional and other project finance;
• completion of the SPP; and
• attendance by the Chief Technology Officer at IMARC and by the Interim Chief Executive Officer at
All-Energy Australia, with meetings planned with downstream developers, regulators and financiers.
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 10
CAPITAL STRUCTURE
The Company’s securities on issue as at the date of this report are set out in Table 2, and the securities
proposed to be issued under the SPP and subject to shareholder approval at the AGM in Table 3.
Table 2 Securities on issue
Securities Number
Fully paid ordinary shares 135,464,148
Unlisted options exercisable at $0.205 expiring 30 June 2028 20,100,000
Unlisted options exercisable at $0.12 expiring 1 March 2029 11,072,607
Table 3 Proposed issues of securities
Proposed issue Number
SPP at $0.06 per share, closing 4 November 2026 (up to) 13,333,333
Idemitsu Subscription at $0.06 per share, subject to shareholder approval at the
AGM (up to)
11,567,657
Redelinghuys Subscription at $0.06 per share, subject to shareholder approval
at the AGM
4,438,667
Shares to Mr McClure at a deemed $0.06 per share in satisfaction of director
fees and expenses of $10,075 owing at 30 September 2026, subject to
shareholder approval at the AGM
167,924
Unquoted options to Harbour City Corporate Pty Ltd exercisable at $0.12 expiring
1 March 2029, in final settlement of its fee arrangements for the June 2026
placement, subject to shareholder approval at the AGM
10,000,000
The Idemitsu subscription comprises 7,053,448 placement shares and up to 4,514,205 shares depending on SPP subscriptions, so
that Idemitsu’s voting power does not exceed its holding of 33.86% before the offer. Full details of the proposed issues are set out
in the notice of meeting for the AGM. Resolution 9 seeks approval for the issue of up to 500,000 shares to Mr McClure; the Company
will issue only the 167,924 shares required to satisfy the amount owing.
ASX ANNOUNCEMENTS
This quarterly report contains information released to ASX, which has been reported in accordance with
the JORC Code (where required). These announcements can be found on the Company’s website at
https://investors.criticalmineralsgroup.com.au/announcements
During the Quarter
Date Announcement
1 July 2026 Change in substantial holding – Idemitsu
14 July 2026 Notice of General Meeting / Proxy Form
20 July 2026 Technical and Financial Pre-Feasibility Study
21 July 2026 Technical and Financial PFS – Supplementary Information
31 July 2026 Quarterly Activities / Appendix 5B Cash Flow Report
12 August 2026 General Meeting – Withdrawal of Resolution 4
12 August 2026 General Meeting Presentation
12 August 2026 Results of Meeting
28 August 2026 Leadership Transition – Pat Kelly Appointed Interim CEO
Quarterly Activities Report – 30 September 2026
criticalmineralsgroup.com.au
(+61) 7 3132 3504 | Level 15, 100 Edward St, Brisbane QLD 4000, Australia 11
Date Announcement
1 September 2026 Application for quotation of securities – CMG
1 September 2026 Notification regarding unquoted securities – CMG
1 September 2026 Cleansing notice
3 September 2026 Change in substantial holding – Idemitsu
4 September 2026 Change of Director’s Interest Notice – S McClure
4 September 2026 Change of Director’s Interest Notice – A Broome
4 September 2026 Change of Director’s Interest Notice – S Winter
4 September 2026 Final Director’s Interest Notice – S Winter
10 September 2026 Ceasing to be a substantial holder
24 September 2026 Notice under Listing Rule 3.13.1
29 September 2026 Annual Report to shareholders
29 September 2026 Appendix 4G
29 September 2026 Corporate Governance Statement
After the Quarter to the date of this report
Date Announcement
19 October 2026 Lindfield PFS Mine Plan Area Fully Secured
19 October 2026
Placement and Share Purchase Plan to raise up to $2.05 million to commence the Lindfield
Vanadium Project Definitive Feasibility Study
19 October 2026 Proposed issue of securities – CMG
19 October 2026 Initial Director’s Interest Notice – G Redelinghuys
20 October 2026 DFS Drilling Program Commences at Lindfield
20 October 2026 Application for quotation of securities – CMG
20 October 2026 Cleansing Notice
21 October 2026 SPP offer booklet dispatched and SPP opens
22 October 2026 Change in substantial holding – Idemitsu
22 October 2026 Becoming a substantial holder – Latimore
FINANCIAL COMMENTARY
The Quarterly Cash Flow Report (Appendix 5B) for the Quarter provides an overview of the Company’s
financial activities.